3468 S KELTON AVE 90034
Certificate Information: 3468 S KELTON AVE 90034
- Application / Permit
- 21014-30000-03198
- Plan Check / Job No.
- B21WL02775
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) Single family dwellilng. Per enginneering design.
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 5/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | JASON JANGADA |
| Corrections Issued | 6/26/2021 | JASON JANGADA |
| Applicant returned to address corrections | 7/13/2021 | JASON JANGADA |
| Applicant returned to address corrections | 7/14/2021 | JASON JANGADA |
| Applicant returned to address corrections | 9/9/2021 | JASON JANGADA |
| Applicant returned to address corrections | 9/28/2021 | ALFREDO JARA |
| Plan Check Approved | 10/18/2021 | ALFREDO JARA |
| Issued | 10/28/2021 | APPLICANT |
| CofO in Progress | 5/24/2023 | MICHAEL PELHAM |
| Permit Finaled | 5/25/2023 | DANIEL ORRANTE |
| CofO Issued | 5/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/12/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 7/23/2021 | VASIL MIHALEV |
| Permit | Cleared | 9/16/2021 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | CATHERINE ADROVER |
| Trees in Parkway | Cleared | 10/12/2021 | ADALBERTO VERA |
Contact Information
| Contractor | Concept Renovations Inc; Lic. No.: 1016942-B | 15928 VENTURA BLVD 225 ENCINO, CA 91436 |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: C35270 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/23/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 7/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 7/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/18/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 7/25/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 7/25/2022 | Partial Approval | JOHNNY MIRANDA |
| Pre-Inspection | 9/30/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2022 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 11/29/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 1/17/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/17/2023 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/17/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 1/25/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 1/25/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/6/2023 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 2/14/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 2/17/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 3/17/2023 | Approved | JOHNNY MIRANDA |
| Final | 4/3/2023 | No Access for Inspection | KENNETH NAGLE |
| Green Building Final | 4/3/2023 | No Access for Inspection | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Not Ready | KENNETH NAGLE |
| Smoke Detectors | 4/3/2023 | No Access for Inspection | KENNETH NAGLE |
| Final | 4/17/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 4/17/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 4/17/2023 | Approved | JOHNNY MIRANDA |
| Final | 5/24/2023 | Conditional Approval | MICHAEL PELHAM |