5310 S PACIFIC AVE 90292
Certificate Information: 5310 S PACIFIC AVE 90292
- Application / Permit
- 21014-30000-03197
- Plan Check / Job No.
- B21WL02774
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major Interior/Exterior remodel and addition to (E) xisiting SFD w/ roof deck and mechanical room
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 7/14/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 7/30/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/13/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 10/29/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 3/11/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 4/18/2022 | FELIPE HERNANDEZ |
| Plan Check Approved | 4/26/2022 | FELIPE HERNANDEZ |
| Issued | 5/3/2022 | APPLICANT |
| CofO in Progress | 2/5/2025 | HERBERT GIRON |
| CofO Issued | 2/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/4/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2021 | SAUL GARCIA |
| Construction within easement | Cleared | 10/8/2021 | RIDWAN HARDY |
| Abandoned oil well | Cleared | 10/22/2021 | KURT CORRAL |
| Coastal Zone | Cleared | 3/1/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 3/1/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 3/1/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 3/1/2022 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 3/11/2022 | IRA BROWN |
Contact Information
| Contractor | Aragon Fine Homes Inc; Lic. No.: 992249-B | 766 NORTH WORKMAN STREET SAN FERNANDO, CA 91340 |
| Engineer | Shirley,, Peter Franklin; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/8/2022 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Partial Approval | DAVID FEILER |
| Wood Frame | 2/3/2023 | Partial Approval | EVAN COOPER |
| Wood Frame | 2/27/2023 | Not Ready for Inspection | EVAN COOPER |
| Deputy Wood Construction | 5/8/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 5/15/2023 | Conditional Approval | EVAN COOPER |
| PLUMBING-Rough | 5/18/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 9/12/2023 | Conditional Approval | HERBERT GIRON |
| Deputy Wood Construction | 9/20/2023 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 11/7/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 11/8/2023 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 11/8/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 11/14/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 11/14/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 11/14/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 12/27/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/27/2023 | Partial Approval | EVAN COOPER |
| Wood Frame | 12/27/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/4/2024 | Partial Approval | HERBERT GIRON |
| Insulation | 1/24/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 2/9/2024 | Partial Approval | HERBERT GIRON |
| Final | 2/9/2024 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 2/9/2024 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 2/21/2024 | Partial Approval | HERBERT GIRON |
| Pre-Inspection | 3/7/2024 | Partial Inspection | HERBERT GIRON |
| Special/Order Compliance | 3/7/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Shower Pan | 4/3/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/8/2024 | Approved | HERBERT GIRON |
| Gas Test | 7/30/2024 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/27/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 12/4/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 1/15/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 1/21/2025 | Approved | EUGENE CASSIDY |
| HVAC-Final | 1/22/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/27/2025 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 1/29/2025 | Approved | HERBERT GIRON |
| Final | 1/29/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 1/29/2025 | Approved | HERBERT GIRON |
| Green Building Final | 1/29/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 1/29/2025 | Approved | HERBERT GIRON |
| Final | 2/5/2025 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 2/5/2025 | Approved | HERBERT GIRON |