8147 N WILKINSON AVE 91605

Certificate Information: 8147 N WILKINSON AVE 91605

Application / Permit
21014-30000-03195
Plan Check / Job No.
B21WL02772
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story ground floor addition to (E) SFD per WFPP. Scope of work to include new bedroom, walk-in closet bathroom, laundry + powder room
Permit Issued
Issued on 8/23/2021
Issuing Office
Current Status
CofO Issued on 6/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2021 APPLICANT
Assigned to Plan Check Engineer 6/23/2021 JASON JANGADA
Corrections Issued 6/24/2021 JASON JANGADA
Applicant returned to address corrections 7/27/2021 KHUONG TRUONG
Issued 8/23/2021 APPLICANT
CofO in Progress 4/21/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 6/20/2022 DANIEL ORRANTE
CofO Issued 6/20/2022 DANIEL ORRANTE
Permit Finaled 6/20/2022 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/15/2021 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 7/30/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/30/2021 GABRIEL ROBLES
Sewer availability Cleared 7/30/2021 GABRIEL ROBLES

Contact Information

Architect Khoudikian,, Kaaren G; Lic. No.: C13183 6906 FOOTHILL BLVD.      TUJUNGA, CA 91042
Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/15/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 10/1/2021 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 10/6/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Insulation 10/6/2021 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 10/27/2021 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/29/2021 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 10/29/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 10/29/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 10/29/2021 Approved CHRISTOPHER DELLEFIELD
Insulation 11/4/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 11/9/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 11/19/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 11/19/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 12/28/2021 Approved DEANDRE HOFFMAN
Shower Pan 12/28/2021 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 4/7/2022 Approved CHRISTOPHER DELLEFIELD
Final 4/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 4/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 4/7/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 4/7/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 4/7/2022 Approved CHRISTOPHER DELLEFIELD
Final 4/21/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
Green Building Final 4/21/2022 Approved CHRISTOPHER DELLEFIELD