5654 N COSTELLO AVE 91401

Certificate Information: 5654 N COSTELLO AVE 91401

Application / Permit
21014-30000-03194
Plan Check / Job No.
B21WL02771
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Enclose (E) entry and one story ground floor addition to (E) SFD per WFPP
Permit Issued
Issued on 9/13/2021
Issuing Office
Current Status
CofO Issued on 6/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2021 APPLICANT
Assigned to Plan Check Engineer 6/23/2021 JASON JANGADA
Corrections Issued 6/23/2021 JASON JANGADA
Applicant returned to address corrections 7/20/2021 JASON JANGADA
Plan Check Approved 8/10/2021 SERGIO SILVA
Issued 9/13/2021 APPLICANT
CofO in Progress 3/10/2022 RICHARD DOCKUS
CofO Issued 6/11/2022 MICHAEL SMITH
Permit Finaled 6/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/2/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 7/2/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/7/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/15/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/29/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 12/10/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Not Ready for Inspection RICHARD DOCKUS
Insulation 12/22/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 12/22/2021 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 12/27/2021 Not Ready for Inspection ALAN MORELOS
BUILDING-Rough-Frame 12/29/2021 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 12/29/2021 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Partial Approval MICHEL ABAJAN
Insulation 1/5/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 No Access for Inspection CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 1/12/2022 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 1/24/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 1/24/2022 Partial Approval ALAN MORELOS
Drywall Nailing 2/3/2022 Corrections Issued RICHARD DOCKUS
Shower Pan 2/3/2022 Approved RICHARD DOCKUS
Green Building Rough 2/8/2022 Approved RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 2/8/2022 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 3/2/2022 Approved RICHARD DOCKUS
Final 3/2/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 3/2/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 3/2/2022 Corrections Issued RICHARD DOCKUS
Final 3/10/2022 OK to Issue CofO RICHARD DOCKUS
Smoke Detectors 3/10/2022 Approved RICHARD DOCKUS