2215 S WALNUT AVE 90291
Certificate Information: 2215 S WALNUT AVE 90291
- Application / Permit
- 21014-30000-03124
- Plan Check / Job No.
- B21WL02727
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel (E) SFD. Per engineering design.
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- CofO Issued on 6/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | ALFREDO JARA |
| Corrections Issued | 6/29/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 8/10/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 9/13/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 9/15/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 10/19/2021 | ALFREDO JARA |
| Plan Check Approved | 11/3/2021 | ALFREDO JARA |
| Issued | 11/8/2021 | APPLICANT |
| Building Plans Picked Up | 11/15/2021 | APPLICANT |
| CofO in Progress | 6/21/2022 | DAVID FEILER |
| Permit Finaled | 6/22/2022 | DANIEL ORRANTE |
| CofO Issued | 6/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/2/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2021 | DINAH GARIN |
| Specific Plan | Cleared | 9/10/2021 | PEDRO AYALA |
Contact Information
| Architect | Ferri,, John C; Lic. No.: C32037 | 4591 OPERETTA DRIVE HUNTINGTON BEACH, CA 92649 |
| Contractor | Specon Corporation; Lic. No.: 938424-B | 17011 BEACH BOULEVARD STE 900 HUNTINGTON BEACH, CA 92647 |
| Engineer | Posadas,, John Garcia; Lic. No.: C30786 | 2063 PASEO LUCINDA SAN DIMAS, CA 91773 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/24/2021 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 12/1/2021 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 1/3/2022 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 1/3/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Wood Construction | 1/5/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 1/11/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 3/17/2022 | Approved | DAVID FEILER |
| Green Building Rough | 3/17/2022 | Approved | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 3/17/2022 | Approved | DAVID FEILER |
| Insulation | 3/23/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/23/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/4/2022 | Approved | STEPHANIE SWANSON |
| Final | 4/4/2022 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 4/11/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 4/18/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 4/28/2022 | Approved | JESUS RODRIGUEZ |
| Final | 6/9/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 6/9/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/9/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 6/9/2022 | Approved | JESUS RODRIGUEZ |
| Final | 6/21/2022 | OK to Issue CofO | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 6/21/2022 | SGSOV Approved | DAVID FEILER |