Remodel and Addition (E) Single family dwelling. Per engineering design.
Permit Issued
Issued on 12/14/2021
Issuing Office
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 ALFREDO JARA
Corrections Issued 7/8/2021 ALFREDO JARA
Quality Review Completed 7/20/2021 CHIHARU SUZUKI
Plan Check Approved 11/26/2021 ALFREDO JARA
Issued 12/14/2021 APPLICANT
Building Plans Picked Up 12/16/2021 APPLICANT
CofO in Progress 1/13/2023 JAVIER RAMOS JR
Permit Finaled 2/14/2023 MICHAEL SMITH
CofO Issued 2/14/2023 MICHAEL SMITH
Permit Finaled 2/14/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/3/2021 LEE GUILBEAUX
Sewer availability Cleared 8/3/2021 LEE GUILBEAUX
Low Impact Development Cleared 10/27/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 10/28/2021 LEE GUILBEAUX

Contact Information

Architect Youssefzadeh,, Atabak; Lic. No.: C22727 438 S PECK DRIVE      BEVERLY HILLS, CA 90212
Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/20/2021 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 12/20/2021 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 12/28/2021 Partial Approval BRENDAN LOONEY
Special/Order Compliance 12/28/2021 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 1/4/2022 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 1/4/2022 Not Ready for Inspection MARK JOHNSON
Excavation/Setback/Form/Re-Bar 1/5/2022 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 1/5/2022 Corrections Issued MARK JOHNSON
Deputy Reinf. Concrete 1/6/2022 No Access for Inspection MARK JOHNSON
Wood Frame 1/27/2022 Partial Approval MICHAEL TEMPLE
ELECTRICAL-Rough 2/24/2022 Partial Approval DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Partial Approval DEANDRE HOFFMAN
PLUMBING-Rough 2/24/2022 Corrections Issued DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 3/3/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/7/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 3/11/2022 Partial Inspection MICHAEL TEMPLE
PLUMBING-Rough 3/11/2022 Partial Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 4/14/2022 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 5/5/2022 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 5/19/2022 Approved RAUL OLAGI
Pre-Inspection 5/19/2022 Approved RAUL OLAGI
Deputy Wood Construction 5/20/2022 Approved DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Partial Approval RAUL OLAGI
HVAC-Rough 5/20/2022 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 5/23/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Approved RAUL OLAGI
PLUMBING-Rough 5/23/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 6/15/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 6/15/2022 Partial Approval JAVIER RAMOS JR
HVAC-Rough 6/15/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/15/2022 Partial Approval JAVIER RAMOS JR
Insulation 6/22/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/29/2022 Approved JAVIER RAMOS JR
Drywall Nailing 6/29/2022 Approved JAVIER RAMOS JR
Green Building Rough 6/29/2022 Approved JAVIER RAMOS JR
Grounding or Bonding 8/15/2022 Approved JAVIER RAMOS JR
Final 10/3/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 10/3/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 10/3/2022 Approved JAVIER RAMOS JR
Final 1/9/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 1/9/2023 Approved JAVIER RAMOS JR