1043 N MARONEY LANE 90272
Certificate Information: 1043 N MARONEY LANE 90272
- Application / Permit
- 21014-30000-03067
- Plan Check / Job No.
- B21WL02678
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and interior remodel to (E) 1 story SFD w/att garage
- Permit Issued
- Issued on 2/9/2022
- Issuing Office
- Current Status
- CofO Issued on 2/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 7/12/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 7/26/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 9/7/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 10/14/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 11/29/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 2/4/2022 | FELIPE HERNANDEZ |
| Issued | 2/9/2022 | APPLICANT |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| CofO in Progress | 12/16/2022 | BRENDAN LOONEY |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
| CofO Issued | 2/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2021 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 8/19/2021 | DENNIS BRAGIN |
| Watercourse | Cleared | 8/19/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 10/14/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 10/14/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 10/14/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 10/14/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 10/14/2021 | DENNIS BRAGIN |
| Low Impact Development | Cleared | 11/10/2021 | NICK RAYGOZA |
| Coastal Zone | Cleared | 1/21/2022 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 2/4/2022 | FELIPE HERNANDEZ |
Contact Information
| Architect | Huddleson,, Hugh W; Lic. No.: C18541 | 333 BUSH STREET APT 3803 SAN FRANCISCO, CA 94104 |
| Contractor | Top Shelf Construction; Lic. No.: 1039370-B | 930 KOHALA STREET OXNARD, CA 93030 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/9/2022 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 3/10/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/10/2022 | Partial Approval | ANDREW NAVE |
| Deputy Drilled-In Anchors | 3/11/2022 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/15/2022 | Approved | ANDREW NAVE |
| Special/Order Compliance | 3/15/2022 | Partial Inspection | PATRICK QUALEY |
| BUILDING-Rough-Frame | 4/11/2022 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 4/11/2022 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 4/19/2022 | Partial Approval | ANDREW NAVE |
| FLOOD-Proofing Certificate | 5/3/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 5/4/2022 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 5/11/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Approved | ANDREW NAVE |
| Green Building Rough | 5/11/2022 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 5/11/2022 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/17/2022 | Approved | ANDREW NAVE |
| Green Building Rough | 5/17/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 5/17/2022 | Corrections Issued | ANDREW NAVE |
| Interior/Exterior Lathing | 5/17/2022 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 5/17/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 5/31/2022 | Approved | ANDREW NAVE |
| Shower Pan | 5/31/2022 | Approved | ANDREW NAVE |
| Insulation | 6/9/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 6/14/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 6/17/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 8/22/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 8/29/2022 | Approved | BRENDAN LOONEY |
| Service/Power Release | 8/31/2022 | Approved | BRENDAN LOONEY |
| Gas Test | 9/12/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 9/12/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 9/26/2022 | Approved | ANDREW NAVE |
| PLUMBING-Final | 9/26/2022 | Corrections Issued | ANDREW NAVE |
| Final | 10/17/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 10/17/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 10/17/2022 | Approved | BRENDAN LOONEY |
| Final | 11/9/2022 | Partial Approval | BRENDAN LOONEY |
| Final | 11/22/2022 | OK to Issue CofO | BRENDAN LOONEY |