11744 W PALMS BLVD 90066

Certificate Information: 11744 W PALMS BLVD 90066

Application / Permit
21014-30000-03056
Plan Check / Job No.
B21WL02673
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Front & rear addition plus a major remodel of an (e) s.f.d.
Permit Issued
Issued on 4/12/2022
Issuing Office
Current Status
CofO Issued on 12/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 KHUONG TRUONG
Corrections Issued 6/26/2021 KHUONG TRUONG
Applicant returned to address corrections 8/2/2021 MANUEL GARCIA
Applicant returned to address corrections 10/29/2021 MANUEL GARCIA
Plan Check Approved 2/22/2022 RICHARD GARCIA
Building Plans Picked Up 2/24/2022 APPLICANT
Issued 4/12/2022 APPLICANT
CofO in Progress 12/5/2022 ASHLEY THOMPSON
Permit Finaled 12/5/2022 DANIEL ORRANTE
CofO Issued 12/5/2022 DANIEL ORRANTE
Permit Finaled 12/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/28/2021 KHUONG TRUONG
Eng Process Fee Ord 176,300 Cleared 7/20/2021 NIKTA MOUSAVI
Sewer availability Cleared 7/20/2021 NIKTA MOUSAVI
Specific Plan Cleared 9/1/2021 ROBERT SANCHEZ
Low Impact Development Cleared 10/7/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 10/12/2021 NIKTA MOUSAVI
Construction near power lines Cleared 11/17/2021 WALTER RAMIREZ
Miscellaneous Cleared 2/11/2022 JENSON LEE

Contact Information

Contractor Bless It Construction Inc; Lic. No.: 1048746-B 1824 E KAY STREET      COMPTON, CA 90221
Engineer Herrera,, Edgar E; Lic. No.: C67603 1929 GREENLEAF DR      WEST COVINA, CA 91792

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/10/2022 Conditional Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 5/10/2022 No Access for Inspection KENNETH NAGLE
Deputy Wood Construction 5/10/2022 No Access for Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 5/11/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 5/11/2022 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 5/31/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 6/2/2022 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/8/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Approval JOHNNY MIRANDA
HVAC-Rough 7/6/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 7/6/2022 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 7/11/2022 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Partial Approval STEPHANIE SWANSON
Green Building Rough 7/11/2022 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 7/11/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 7/11/2022 Approved STEPHANIE SWANSON
Deputy Wood Construction 7/14/2022 Conditional Approval JOHNNY MIRANDA
ELECTRICAL-Rough 7/26/2022 Corrections Issued JOHNNY MIRANDA
Wood Frame 7/26/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 7/29/2022 Approved JOHNNY MIRANDA
Insulation 7/29/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 7/29/2022 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 7/29/2022 Approved JOHNNY MIRANDA
Insulation 8/2/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 8/2/2022 Approved JOHN KIDWELL
Drywall Nailing 8/5/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 8/12/2022 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 10/13/2022 SGSOV Not Ready JOHNNY MIRANDA
ELECTRICAL-Final 10/19/2022 Not Ready for Inspection HERBERT GIRON
Gas Test 10/19/2022 Approved HERBERT GIRON
HVAC-Final 10/19/2022 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 10/19/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 10/21/2022 Approved JOHNNY MIRANDA
HVAC-Final 10/21/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 10/21/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 12/2/2022 Approved ASHLEY THOMPSON
Final 12/2/2022 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 12/2/2022 Approved ASHLEY THOMPSON
Green Building Final 12/2/2022 Approved ASHLEY THOMPSON
Green Building Rough 12/2/2022 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 12/2/2022 Approved ASHLEY THOMPSON