15908 W GAULT ST 91406
Certificate Information: 15908 W GAULT ST 91406
- Application / Permit
- 21014-30000-03049
- Plan Check / Job No.
- B21WL02660
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) Garage conversion to ADU and addition to ADU PER WFPP. PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 11/24/2021
- Issuing Office
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | ALFREDO JARA |
| Corrections Issued | 6/29/2021 | ALFREDO JARA |
| Plan Check Approved | 10/8/2021 | ALFREDO JARA |
| Issued | 11/24/2021 | APPLICANT |
| CofO in Progress | 1/30/2024 | RAUL OLAGI |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
| CofO Issued | 3/18/2024 | RUBEN SALAS |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/8/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/15/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/25/2021 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/27/2022 | No Access for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 5/31/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/24/2024 | Approved | RAUL OLAGI |
| Drywall Nailing | 1/24/2024 | Approved | RAUL OLAGI |
| Final | 1/24/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 1/24/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 1/24/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 1/24/2024 | Approved | RAUL OLAGI |
| Final | 1/30/2024 | OK to Issue CofO | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/30/2024 | SGSOV Approved | RAUL OLAGI |