520 N VIA DE LA PAZ 90272
Certificate Information: 520 N VIA DE LA PAZ 90272
- Application / Permit
- 21014-30000-03047
- Plan Check / Job No.
- B21WL02654
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st (109 sf) and 2nd (755 sf) story addition and remodel to (e) 2-story SFD (3,131 sf), (Total SFD floor area = 3995 sf)
- Permit Issued
- Issued on 4/15/2022
- Issuing Office
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | REZA HAGHIGHAT |
| Corrections Issued | 7/6/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 7/12/2021 | CHIHARU SUZUKI |
| Plan Check Approved | 1/17/2022 | REZA HAGHIGHAT |
| Building Plans Picked Up | 1/20/2022 | APPLICANT |
| Issued | 4/15/2022 | APPLICANT |
| CofO in Progress | 10/25/2024 | EVAN COOPER |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
| CofO Issued | 11/19/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/16/2021 | ANTHONY MAINEZ |
| Coastal Zone | Cleared | 11/15/2021 | ANNA VIDAL |
| Low Impact Development | Cleared | 12/10/2021 | JONATAN VELASQUEZ |
| GPI Written Notices | Cleared | 1/17/2022 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 1/17/2022 | REZA HAGHIGHAT |
| Roof/Waste drainage to street | Cleared | 1/21/2022 | ABEL CASILLAS |
Contact Information
| Architect | Jewell,, Ward E; Lic. No.: C26187 | 7825 HENEFER AVE LOS ANGELES, CA 90045 |
| Contractor | Reynolds David Builder Inc; Lic. No.: 987887-B | 3492 CARL COURT NEWBURY PARK, CA 91320 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2022 | Approved | ANDREW NAVE |
| Deputy Drilled-In Anchors | 6/9/2022 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/9/2022 | Partial Approval | ANDREW NAVE |
| Wood Frame | 6/15/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 9/26/2022 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 2/22/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Corrections Issued | STEPHANIE SWANSON |
| Special/Order Compliance | 2/27/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 3/1/2023 | Corrections Issued | BRENDAN LOONEY |
| Reinforced Concrete Frame | 3/1/2023 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 3/8/2023 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Partial Approval | BRENDAN LOONEY |
| HVAC-Rough | 3/17/2023 | Partial Approval | BRENDAN LOONEY |
| HVAC-Rough | 3/31/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/31/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/4/2023 | Approved | BRENDAN LOONEY |
| Green Building Rough | 4/4/2023 | Approved | BRENDAN LOONEY |
| Insulation | 4/19/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 4/19/2023 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 6/1/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 6/1/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 6/5/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/3/2024 | Not Ready for Inspection | EVAN COOPER |
| Final | 5/3/2024 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 5/3/2024 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 5/3/2024 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 5/3/2024 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 5/3/2024 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Not Ready | EVAN COOPER |
| Service/Power Release | 5/3/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 5/3/2024 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 5/30/2024 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 6/7/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 9/9/2024 | Corrections Issued | EVAN COOPER |
| Final | 9/9/2024 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 9/9/2024 | Approved | EVAN COOPER |
| Green Building Final | 9/9/2024 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 9/9/2024 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/9/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 9/9/2024 | Approved | EVAN COOPER |
| Special/Order Compliance | 9/11/2024 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 9/13/2024 | Approved | EVAN COOPER |
| Final | 9/13/2024 | Corrections Issued | EVAN COOPER |
| Green Building Final | 9/13/2024 | Approved | EVAN COOPER |
| HVAC-Final | 9/13/2024 | Approved | EVAN COOPER |
| Final | 10/2/2024 | Not Ready for Inspection | EVAN COOPER |
| Final | 10/24/2024 | OK to Issue CofO | EVAN COOPER |