19156 W WELLS DR 91356

Certificate Information: 19156 W WELLS DR 91356

Application / Permit
21014-30000-02894
Plan Check / Job No.
B21WL02542
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO SFD
Permit Issued
Issued on 3/7/2022
Issuing Office
Current Status
CofO Issued on 12/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 KHUONG TRUONG
Corrections Issued 6/12/2021 KHUONG TRUONG
Plan Check Approved 8/19/2021 KHUONG TRUONG
Issued 3/7/2022 APPLICANT
CofO in Progress 12/27/2022 DAVID SANDOVAL
Permit Finaled 12/28/2022 MICHAEL SMITH
CofO Issued 12/28/2022 MICHAEL SMITH
Permit Finaled 12/28/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/26/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/27/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 8/19/2021 KHUONG TRUONG

Contact Information

Contractor Owner-Builder       ,
Engineer Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/24/2022 Partial Approval ROBERT GOLD
Footing/Foundation/Slab 3/25/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 3/30/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Corrections Issued DAVID SANDOVAL
Deputy Drilled-In Anchors 5/6/2022 Conditional Approval DAVID SANDOVAL
Deputy Wood Construction 5/6/2022 Conditional Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/11/2022 Approved DAVID SANDOVAL
Green Building Rough 5/11/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 5/13/2022 Approved DAVID SANDOVAL
HVAC-Rough 5/13/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 5/13/2022 Approved DAVID SANDOVAL
Green Building Rough 5/17/2022 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 5/17/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 5/19/2022 Approved DAVID SANDOVAL
Green Building Rough 5/19/2022 Approved DAVID SANDOVAL
Insulation 5/19/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 5/19/2022 Partial Approval DAVID SANDOVAL
Drywall Nailing 5/26/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 5/26/2022 Partial Approval MORRIS JACKSON
Final 9/6/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 9/6/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 9/6/2022 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 9/6/2022 Approved DAVID SANDOVAL
ELECTRICAL-Final 11/7/2022 Approved DAVID SANDOVAL
Final 11/7/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 11/7/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Final 11/7/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Final 11/7/2022 Approved DAVID SANDOVAL
Final 12/27/2022 OK to Issue CofO DAVID SANDOVAL
Green Building Final 12/27/2022 Approved DAVID SANDOVAL