8302 W 4TH ST 90048
Certificate Information: 8302 W 4TH ST 90048
- Application / Permit
- 21014-30000-02876
- Plan Check / Job No.
- B21WL02514
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Bedroom extension at rear of (E) single story SFD.
- Permit Issued
- Issued on 2/9/2022
- Issuing Office
- Current Status
- CofO Issued on 9/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 6/9/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 6/28/2021 | KHUONG TRUONG |
| Issued | 2/9/2022 | APPLICANT |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| CofO in Progress | 8/29/2023 | DAVID FEILER |
| Permit Finaled | 9/8/2023 | DANIEL ORRANTE |
| CofO Issued | 9/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | CECILIO NAVARRO |
Contact Information
| Architect | Grant,, James Bertrand; Lic. No.: C14444 | 1782 KELTON AVENUE LOS ANGELES, CA 90024 |
| Contractor | Kavin Fence And Construction Company; Lic. No.: 356032-B | 3814 WILLAT AVENUE CULVER CITY, CA 90232 |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: C49104 | 1434 WESTWOOD BLVD ST 17 LOS ANGELES, CA 90024 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/11/2022 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/15/2022 | Approved | EVAN COOPER |
| METHANE-Barrier | 2/15/2022 | Approved | EVAN COOPER |
| METHANE-Subgrade | 2/15/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Partial Approval | EVAN COOPER |
| Wood Frame | 5/13/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 12/19/2022 | Partial Approval | JEREMY TODD |
| Green Building Rough | 12/19/2022 | Approved | JEREMY TODD |
| METHANE-Rough | 12/19/2022 | Approved | JEREMY TODD |
| Rough-Elec/Plmb/HVAC | 12/19/2022 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 1/26/2023 | Approved | JEREMY TODD |
| Insulation | 2/2/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 2/14/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 6/7/2023 | Approved | JEREMY TODD |
| Final | 6/7/2023 | Corrections Issued | JEREMY TODD |
| Green Building Final | 6/7/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 6/7/2023 | Approved | JEREMY TODD |
| Final | 8/25/2023 | OK to Issue CofO | MEL KHACHATOURIAN |