1920 S VICTORIA AVE 90016

Certificate Information: 1920 S VICTORIA AVE 90016

Application / Permit
21014-30000-02823
Plan Check / Job No.
B21WL02487
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition & remodel to (e) S.F.D. Per engineering design.
Permit Issued
Issued on 10/12/2021
Issuing Office
Current Status
Issued on 10/12/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/7/2021 ALFREDO JARA
Corrections Issued 6/11/2021 ALFREDO JARA
Applicant returned to address corrections 7/27/2021 ALFREDO JARA
Plan Check Approved 8/12/2021 JASON JANGADA
Issued 10/12/2021 APPLICANT
Building Plans Picked Up 12/9/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/31/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 8/2/2021 THOMAS LANG

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Grenier Construction; Lic. No.: 636045-B 22643 COVELLO STREET      WEST HILLS, CA 91307

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/21/2021 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 10/21/2021 Conditional Approval STUART CHAPMAN
Special/Order Compliance 10/21/2021 Approved JOSE AVILA
ELECTRICAL-Rough 12/3/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Partial Approval STUART CHAPMAN
Green Building Rough 12/3/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 12/3/2021 Approved STUART CHAPMAN
PLUMBING-Rough 12/3/2021 Approved STUART CHAPMAN
Insulation 2/4/2022 Corrections Issued STUART CHAPMAN
Service/Power Release 2/4/2022 Approved STUART CHAPMAN
Insulation 2/11/2022 Approved AMY COLIN
Interior/Exterior Lathing 2/11/2022 Approved AMY COLIN
BUILDING-Rough-Frame 4/4/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 4/4/2022 Approved STUART CHAPMAN
Final 4/4/2022 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 4/4/2022 Approved STUART CHAPMAN
Green Building Final 4/4/2022 Approved STUART CHAPMAN
Green Building Rough 4/4/2022 Approved STUART CHAPMAN
HVAC-Final 4/4/2022 Corrections Issued STUART CHAPMAN
METHANE-Barrier 4/4/2022 Approved STUART CHAPMAN
METHANE-Subgrade 4/4/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/4/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 4/4/2022 Approved STUART CHAPMAN