4245 N CLYBOURN AVE 91602

Certificate Information: 4245 N CLYBOURN AVE 91602

Application / Permit
21014-30000-02817
Plan Check / Job No.
B21WL02483
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel and addtion of new deck on the second floor. Update roofing above sun room
Permit Issued
Issued on 9/9/2021
Issuing Office
Current Status
Issued on 9/9/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/5/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 FELIPE HERNANDEZ
Corrections Issued 6/25/2021 FELIPE HERNANDEZ
Quality Review Completed 7/6/2021 TARIK SAOUD
Applicant returned to address corrections 8/4/2021 FELIPE HERNANDEZ
Plan Check Approved 8/30/2021 FELIPE HERNANDEZ
Issued 9/9/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/5/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/9/2021 GABRIEL ROBLES

Contact Information

Contractor D C & C Construction Corp; Lic. No.: 1051774-B 11888 PEORIA STREET      SUN VALLEY, CA 91352
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/12/2021 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 10/15/2021 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 11/12/2021 Approved ARAM AVEDISIAN
Deputy Reinf. Concrete 11/16/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 11/30/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 2/25/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 2/25/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 3/3/2022 Approved CALEB MEISTER
HVAC-Rough 3/3/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 3/3/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 4/7/2022 Approved THOMAS FINNILA
PLUMBING-Rough 4/7/2022 Approved THOMAS FINNILA
Deputy Wood Construction 4/27/2022 Conditional Approval DAVID MATSON
Wood Frame 4/28/2022 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 5/20/2022 Approved THOMAS FINNILA
Green Building Rough 5/20/2022 Approved THOMAS FINNILA
Insulation 5/27/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/27/2022 Partial Approval THOMAS FINNILA
Shower Pan 5/27/2022 Approved THOMAS FINNILA
Drywall Nailing 6/7/2022 Approved CALEB MEISTER
ELECTRICAL-Final 4/3/2023 Approved JACK KARGODORIAN
HVAC-Final 4/3/2023 Approved JACK KARGODORIAN
PLUMBING-Final 4/3/2023 Approved JACK KARGODORIAN
Final 6/12/2023 Partial Inspection JACK KARGODORIAN
Green Building Final 6/12/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/12/2023 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 6/12/2023 Approved JACK KARGODORIAN