3314 S MALCOLM AVE 90034
Certificate Information: 3314 S MALCOLM AVE 90034
- Application / Permit
- 21014-30000-02806
- Plan Check / Job No.
- B21WL02464
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (E) 2-story single family dwelling with attached garrage, enclose second floor covered patio to enlarge the (E) bedroom 5'-1" x 19'-9 1/2", remove (E) sunroom and add to the deck 5'-4" x 23'-0". No Sqft added to building
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/6/2023
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2021 | MARJAN SHENASI |
| Corrections Issued | 6/8/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 10/5/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 10/20/2021 | KHUONG TRUONG |
| Issued | 6/16/2022 | APPLICANT |
| Permit Finaled | 6/5/2023 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/13/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | DINAH GARIN |
| Specific Plan | Cleared | 8/27/2021 | PETE EYRE |
| Grading Pre-Inspection | Cleared | 10/5/2021 | JAHANSHAH POURHASSAN |
Contact Information
| Contractor | Misong Corporation; Lic. No.: 755122-B | 936 S ALVARADO STREET LOS ANGELES, CA 90006 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/4/2022 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 8/8/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 8/10/2022 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 8/15/2022 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 8/18/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 11/2/2022 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/2/2022 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 11/9/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 11/9/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/9/2022 | Approved | JOHNNY MIRANDA |
| Deputy Wood Construction | 11/14/2022 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 11/15/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 12/19/2022 | Not Ready for Inspection | KENNETH NAGLE |
| Insulation | 12/19/2022 | Not Ready for Inspection | KENNETH NAGLE |
| Interior/Exterior Lathing | 12/19/2022 | Not Ready for Inspection | KENNETH NAGLE |
| Special/Order Compliance | 12/19/2022 | Corrections Issued | KENNETH NAGLE |
| Drywall Nailing | 12/22/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 12/22/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/22/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 12/22/2022 | Corrections Issued | JOHNNY MIRANDA |
| Shower Pan | 12/29/2022 | Corrections Issued | JOHNNY MIRANDA |
| Shower Pan | 2/1/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 2/16/2023 | Approved | JOHNNY MIRANDA |
| Wood Frame | 2/16/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Wood Frame | 3/23/2023 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/6/2023 | Partial Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/14/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 4/14/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 4/14/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 4/14/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 4/14/2023 | Approved | JOHNNY MIRANDA |
| Final | 5/31/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 5/31/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/31/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 5/31/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/5/2023 | Permit Finaled | JOHNNY MIRANDA |