3314 S MALCOLM AVE 90034

Certificate Information: 3314 S MALCOLM AVE 90034

Application / Permit
21014-30000-02806
Plan Check / Job No.
B21WL02464
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel (E) 2-story single family dwelling with attached garrage, enclose second floor covered patio to enlarge the (E) bedroom 5'-1" x 19'-9 1/2", remove (E) sunroom and add to the deck 5'-4" x 23'-0". No Sqft added to building
Permit Issued
Issued on 6/16/2022
Issuing Office
Metro
Current Status
Permit Finaled on 6/6/2023

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/7/2021 MARJAN SHENASI
Corrections Issued 6/8/2021 MARJAN SHENASI
Applicant returned to address corrections 10/5/2021 JAHANSHAH POURHASSAN
Plan Check Approved 10/20/2021 KHUONG TRUONG
Issued 6/16/2022 APPLICANT
Permit Finaled 6/5/2023 JOHNNY MIRANDA

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/13/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/20/2021 DINAH GARIN
Specific Plan Cleared 8/27/2021 PETE EYRE
Grading Pre-Inspection Cleared 10/5/2021 JAHANSHAH POURHASSAN

Contact Information

Contractor Misong Corporation; Lic. No.: 755122-B 936 S ALVARADO STREET      LOS ANGELES, CA 90006
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/4/2022 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 8/8/2022 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 8/10/2022 Conditional Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 8/15/2022 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 8/18/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 11/2/2022 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 11/2/2022 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 11/9/2022 Approved JOHNNY MIRANDA
HVAC-Rough 11/9/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 11/9/2022 Approved JOHNNY MIRANDA
Deputy Wood Construction 11/14/2022 Conditional Approval JOHNNY MIRANDA
Deputy Wood Construction 11/15/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Approved JOHNNY MIRANDA
Drywall Nailing 12/19/2022 Not Ready for Inspection KENNETH NAGLE
Insulation 12/19/2022 Not Ready for Inspection KENNETH NAGLE
Interior/Exterior Lathing 12/19/2022 Not Ready for Inspection KENNETH NAGLE
Special/Order Compliance 12/19/2022 Corrections Issued KENNETH NAGLE
Drywall Nailing 12/22/2022 Not Ready for Inspection JOHNNY MIRANDA
Insulation 12/22/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 12/22/2022 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 12/22/2022 Corrections Issued JOHNNY MIRANDA
Shower Pan 12/29/2022 Corrections Issued JOHNNY MIRANDA
Shower Pan 2/1/2023 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 2/16/2023 Approved JOHNNY MIRANDA
Wood Frame 2/16/2023 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 3/23/2023 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 4/6/2023 Partial Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 4/14/2023 Approved JOHNNY MIRANDA
Drywall Nailing 4/14/2023 Approved JOHNNY MIRANDA
Green Building Rough 4/14/2023 Approved JOHNNY MIRANDA
Insulation 4/14/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 4/14/2023 Approved JOHNNY MIRANDA
Final 5/31/2023 Corrections Issued JOHNNY MIRANDA
Green Building Final 5/31/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/31/2023 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 5/31/2023 Approved JOHNNY MIRANDA
Final 6/5/2023 Permit Finaled JOHNNY MIRANDA