960 N ROSCOMARE ROAD 90077
Certificate Information: 960 N ROSCOMARE ROAD 90077
- Application / Permit
- 21014-30000-02780
- Plan Check / Job No.
- B21WL02444
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition (389 sf) and remodel to (e) single story SFD (2,973 sf) w./ att. 2-car garage (374 sf)
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2021 | REZA HAGHIGHAT |
| Corrections Issued | 6/28/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 7/7/2021 | TARIK SAOUD |
| Plan Check Approved | 10/20/2021 | REZA HAGHIGHAT |
| Issued | 11/23/2021 | APPLICANT |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| CofO in Progress | 2/1/2024 | CHRISTOPHER WILSON |
| CofO in Progress | 2/1/2024 | CHRISTOPHER WILSON |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
| CofO Issued | 2/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/6/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 8/6/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2021 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 8/19/2021 | PATRICK MISCHLICH |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Owner-Builder | , |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/11/2022 | Approved | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 2/18/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 2/22/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 3/18/2022 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 3/18/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 4/15/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/21/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 4/29/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/19/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Other (see comments) | 5/20/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/23/2022 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 6/1/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 6/1/2022 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/19/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 7/19/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 7/19/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/19/2022 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 7/19/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 7/22/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/22/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 7/26/2022 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 7/26/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 8/9/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 8/10/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 8/26/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 10/11/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 10/12/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Gas Test | 11/21/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 11/21/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/21/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/5/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/5/2022 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/13/2022 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 1/5/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 1/5/2023 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 1/5/2023 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 1/5/2023 | Approved | CHRISTOPHER WILSON |
| Insulation | 1/11/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 1/18/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/18/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/18/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 6/30/2023 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 6/30/2023 | Approved | CHRISTOPHER WILSON |
| Final | 11/16/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/16/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 11/16/2023 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 11/16/2023 | Approved | CHRISTOPHER WILSON |
| Final | 1/11/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 1/16/2024 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 1/16/2024 | Approved | CHRISTOPHER WILSON |
| Final | 1/23/2024 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Final | 1/25/2024 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 1/26/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 1/31/2024 | OK to Issue CofO | CHRISTOPHER WILSON |
| PLUMBING-Final | 1/31/2024 | Approved | CHRISTOPHER WILSON |