1514 W 255TH ST 90710
Certificate Information: 1514 W 255TH ST 90710
- Application / Permit
- 21014-30000-02755
- Plan Check / Job No.
- B21WL02428
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADU conversion and (n) addition of (E) detached garage per LAMC 12.22 A.33(c) and (d), and WFPP
- Permit Issued
- Issued on 11/13/2021
- Issuing Office
- Current Status
- CofO Issued on 4/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | RICHARD GARCIA |
| Corrections Issued | 6/5/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 10/1/2021 | JASON JANGADA |
| Plan Check Approved | 10/18/2021 | KHUONG TRUONG |
| Issued | 11/13/2021 | APPLICANT |
| Building Plans Picked Up | 11/16/2021 | APPLICANT |
| CofO in Progress | 4/10/2023 | EUGENE CASSIDY |
| CofO Issued | 4/13/2023 | ANSON MAGLASANG |
| Permit Finaled | 4/13/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2021 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 9/3/2021 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 9/15/2021 | JOSE HERNANDEZ |
Contact Information
| Contractor | M K Builders; Lic. No.: 907501-B | 1103 WEST 160TH STREET GARDENA, CA 90247 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/21/2021 | Partial Approval | ANSON MAGLASANG |
| Deputy Drilled-In Anchors | 1/20/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/31/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 1/31/2022 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 1/31/2022 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 2/9/2022 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/9/2022 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/15/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 4/15/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 4/15/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 4/15/2022 | Approved | JOHN KLARIN |
| METHANE-Rough | 4/15/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 4/15/2022 | Approved | JOHN KLARIN |
| Underground Mechanical | 4/15/2022 | Approved | JOHN KLARIN |
| Wood Frame | 4/15/2022 | Approved | JOHN KLARIN |
| Insulation | 4/25/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/25/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 5/5/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/11/2022 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 7/11/2022 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 7/11/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/19/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/19/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 10/19/2022 | Approved | EUGENE CASSIDY |
| Final | 11/16/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 11/16/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/6/2023 | Approved | EUGENE CASSIDY |
| Final | 4/6/2023 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 4/6/2023 | Approved | EUGENE CASSIDY |
| HVAC-Final | 4/6/2023 | Approved | EUGENE CASSIDY |