14313 W HATTERAS ST 91401
Certificate Information: 14313 W HATTERAS ST 91401
- Application / Permit
- 21014-30000-02738
- Plan Check / Job No.
- B21WL02416
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION AND ASSOCIATED ALTERATION REPAIR TO EXISTING SINGLE FAMILY DWELLING, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 12/17/2021
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | SERGIO SILVA |
| Corrections Issued | 6/23/2021 | SERGIO SILVA |
| Quality Review Completed | 6/30/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 11/10/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 12/9/2021 | SERGIO SILVA |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| Plan Check Approved | 12/17/2021 | SERGIO SILVA |
| Issued | 12/17/2021 | APPLICANT |
| CofO in Progress | 9/21/2023 | RYAN SALAZAR |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
| CofO Issued | 11/14/2023 | RUBEN SALAS |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 7/16/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/20/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 10/19/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 10/25/2021 | ABDULLAH SADOZAI |
| Green Code | Cleared | 12/9/2021 | SERGIO SILVA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/25/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 2/15/2022 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 2/15/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Insulation | 2/15/2022 | Partial Approval | RICHARD DOCKUS |
| Deputy Wood Construction | 3/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/4/2022 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 3/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Interior/Exterior Lathing | 3/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 5/9/2022 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/9/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 5/9/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 5/9/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 5/9/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 5/9/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 6/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/2/2022 | No Access for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/3/2022 | Partial Approval | RICHARD DOCKUS |
| Insulation | 6/27/2022 | Approved | MICHAEL SMITH |
| Drywall Nailing | 7/7/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 1/10/2023 | Corrections Issued | JOHN COLEMAN |
| HVAC-Final | 1/10/2023 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Final | 1/10/2023 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Final | 6/28/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 6/28/2023 | Corrections Issued | RYAN SALAZAR |
| HVAC-Final | 6/28/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 6/28/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 8/29/2023 | Approved | RYAN SALAZAR |
| Final | 9/20/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 9/20/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 9/20/2023 | Approved | RYAN SALAZAR |