18741 W MAYALL ST 91324

Certificate Information: 18741 W MAYALL ST 91324

Application / Permit
21014-30000-02699
Plan Check / Job No.
B21WL02368
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to (E) 1-Story SFD w/att garage
Permit Issued
Issued on 5/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 FELIPE HERNANDEZ
Corrections Issued 7/9/2021 FELIPE HERNANDEZ
Quality Review Completed 7/26/2021 CHIHARU SUZUKI
Applicant returned to address corrections 10/6/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 10/28/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 11/15/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 12/15/2021 FELIPE HERNANDEZ
Plan Check Approved 12/30/2021 FELIPE HERNANDEZ
Building Plans Picked Up 1/24/2022 APPLICANT
Issued 5/27/2022 APPLICANT
CofO in Progress 10/24/2023 DAVID SCANTLIN
Permit Finaled 10/25/2023 JOHN JANSON
CofO Issued 10/25/2023 JOHN JANSON
Permit Finaled 10/25/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/6/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 10/14/2021 DAGOVERTO GUERRERO

Contact Information

Architect Norris,, Tommy; Lic. No.: C37119 475 WASHINGTON BLVD      MARINA DEL REY, CA 90292
Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/11/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Approved DAVID SCANTLIN
Green Building Rough 3/22/2023 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 5/1/2023 Corrections Issued JOHN KIDWELL
Shower Pan 5/8/2023 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 5/30/2023 Approved JUSTIN HAWLEY
Shower Pan 5/30/2023 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 6/2/2023 Approved JOHN KIDWELL
Drywall Nailing 6/2/2023 Approved JOHN KIDWELL
Green Building Rough 6/2/2023 Approved JOHN KIDWELL
Final 8/31/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 8/31/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 8/31/2023 Not Ready for Inspection DAVID SCANTLIN
Final 10/23/2023 OK to Issue CofO DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 10/23/2023 Approved DAVID SCANTLIN