18741 W MAYALL ST 91324
Certificate Information: 18741 W MAYALL ST 91324
- Application / Permit
- 21014-30000-02699
- Plan Check / Job No.
- B21WL02368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) 1-Story SFD w/att garage
- Permit Issued
- Issued on 5/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 7/9/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 7/26/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/6/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 10/28/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 11/15/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 12/15/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 12/30/2021 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Issued | 5/27/2022 | APPLICANT |
| CofO in Progress | 10/24/2023 | DAVID SCANTLIN |
| Permit Finaled | 10/25/2023 | JOHN JANSON |
| CofO Issued | 10/25/2023 | JOHN JANSON |
| Permit Finaled | 10/25/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 10/14/2021 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Norris,, Tommy; Lic. No.: C37119 | 475 WASHINGTON BLVD MARINA DEL REY, CA 90292 |
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/11/2022 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/1/2023 | Corrections Issued | JOHN KIDWELL |
| Shower Pan | 5/8/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/30/2023 | Approved | JUSTIN HAWLEY |
| Shower Pan | 5/30/2023 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/2/2023 | Approved | JOHN KIDWELL |
| Drywall Nailing | 6/2/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 6/2/2023 | Approved | JOHN KIDWELL |
| Final | 8/31/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 8/31/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 8/31/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 10/23/2023 | OK to Issue CofO | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 10/23/2023 | Approved | DAVID SCANTLIN |