17 S BEVERLY PARK 90210
Certificate Information: 17 S BEVERLY PARK 90210
- Application / Permit
- 21014-30000-02694
- Plan Check / Job No.
- B21WL02357
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Construct two (2) 10' 7" x 15' 6" new balconies adjacent to (e) rear balcony of (E) SFD
- Permit Issued
- Issued on 7/26/2021
- Issuing Office
- Current Status
- Issued on 7/26/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | JASON JANGADA |
| Corrections Issued | 6/5/2021 | JASON JANGADA |
| Applicant returned to address corrections | 7/14/2021 | JASON JANGADA |
| Plan Check Approved | 7/21/2021 | KHUONG TRUONG |
| Issued | 7/26/2021 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 6/8/2021 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 6/11/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 6/17/2021 | DINAH GARIN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Marksmen Building & Design; Lic. No.: 984775-B | 1440 BEAUMONT AVENUE #A2-282 BEAUMONT, CA 92223 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/28/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Reinf. Concrete | 8/2/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/17/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 9/16/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/6/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 10/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 11/24/2021 | Not Ready for Inspection | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 12/3/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 12/3/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 12/3/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 12/3/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 2/24/2022 | Partial Approval | BRENDAN LOONEY |
| Final | 2/10/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 2/10/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 2/10/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |