1207 E VIENNA WAY 90291
Certificate Information: 1207 E VIENNA WAY 90291
- Application / Permit
- 21014-30000-02662
- Plan Check / Job No.
- B21WL02308
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2-Story Addition and Partial Converstion of (E) Garage to ADU per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/2/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2021 | DAVID CASTILLO |
| Corrections Issued | 7/8/2021 | DAVID CASTILLO |
| Quality Review Completed | 7/12/2021 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/24/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 12/13/2022 | DAVID CASTILLO |
| Plan Check Approved | 2/3/2023 | DAVID CASTILLO |
| Building Plans Picked Up | 2/7/2023 | APPLICANT |
| Issued | 3/2/2023 | APPLICANT |
| CofO in Progress | 10/22/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 10/27/2025 | RICHARD STEINBACH |
| CofO Issued | 10/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 1/10/2022 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 2/15/2022 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 2/17/2022 | RIDWAN HARDY |
| Specific Plan | Cleared | 3/8/2022 | PEDRO AYALA |
| Low Impact Development | Cleared | 8/19/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 8/27/2022 | SAUL GARCIA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/26/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 7/11/2023 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 7/21/2023 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 9/1/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 9/1/2023 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/22/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 10/19/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Pre-Inspection | 2/2/2024 | Partial Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 3/19/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 4/24/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 4/24/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 4/24/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 4/29/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/29/2024 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 4/29/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/7/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/16/2024 | Approved | HERBERT GIRON |
| Green Building Rough | 5/16/2024 | Approved | HERBERT GIRON |
| Pre-Inspection | 5/23/2024 | Partial Inspection | HERBERT GIRON |
| Insulation | 6/10/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 6/17/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 6/17/2024 | Approved | HERBERT GIRON |
| Shower Pan | 6/17/2024 | Approved | HERBERT GIRON |
| Service/Power Release | 7/1/2024 | Corrections Issued | HERBERT GIRON |
| Pre-Inspection | 7/15/2024 | Partial Inspection | HERBERT GIRON |
| Service/Power Release | 7/22/2024 | Corrections Issued | HERBERT GIRON |
| Service/Power Release | 7/31/2024 | Partial Inspection | HERBERT GIRON |
| Gas Test | 9/4/2024 | Approved | TEMISTOCLES CAAL |
| Sewer | 10/18/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 10/30/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 12/9/2024 | Approved | HERBERT GIRON |
| Final | 8/25/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 8/25/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 8/25/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 8/25/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Approved | MICHAEL ALLEN |
| Final | 10/21/2025 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 10/21/2025 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/21/2025 | Approved | JESUS RODRIGUEZ |