5943 N MELVIN AVE 91356
Certificate Information: 5943 N MELVIN AVE 91356
- Application / Permit
- 21014-30000-02611
- Plan Check / Job No.
- B21WL02243
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- BEDROOM AND BATHROOM ADDITION TO (E) 1-STORY SFD
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | JASON JANGADA |
| Corrections Issued | 5/26/2021 | JASON JANGADA |
| Plan Check Approved | 7/20/2021 | MANUEL GARCIA |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 8/27/2022 | SEAN HAUPT |
| CofO Issued | 8/31/2022 | MICHAEL SMITH |
| Permit Finaled | 8/31/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/18/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/18/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pouraghabagher,, Ali; Lic. No.: C56013 | PO BOX 244 WOODLAND HILLS, CA 91365 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/9/2022 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/11/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 5/11/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 5/18/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/13/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 6/13/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 6/13/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 6/13/2022 | Approved | SEAN HAUPT |
| Insulation | 6/21/2022 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 6/21/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 6/29/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 6/29/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 8/17/2022 | Approved | VINCENT HANLEY |
| Final | 8/17/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 8/17/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/17/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 8/17/2022 | Approved | VINCENT HANLEY |
| Final | 8/26/2022 | Partial Approval | SEAN HAUPT |