5943 N MELVIN AVE 91356

Certificate Information: 5943 N MELVIN AVE 91356

Application / Permit
21014-30000-02611
Plan Check / Job No.
B21WL02243
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
BEDROOM AND BATHROOM ADDITION TO (E) 1-STORY SFD
Permit Issued
Issued on 8/19/2021
Issuing Office
Current Status
CofO Issued on 8/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 JASON JANGADA
Corrections Issued 5/26/2021 JASON JANGADA
Plan Check Approved 7/20/2021 MANUEL GARCIA
Issued 8/19/2021 APPLICANT
CofO in Progress 8/27/2022 SEAN HAUPT
CofO Issued 8/31/2022 MICHAEL SMITH
Permit Finaled 8/31/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/18/2021 ADRIAN CASTRO
Sewer availability Cleared 6/18/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/29/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Pouraghabagher,, Ali; Lic. No.: C56013 PO BOX 244      WOODLAND HILLS, CA 91365

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/9/2022 Conditional Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 5/11/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 5/11/2022 Approved SEAN HAUPT
PLUMBING-Rough 5/18/2022 Approved MORRIS JACKSON
BUILDING-Rough-Frame 6/13/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 6/13/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Approved SEAN HAUPT
Green Building Rough 6/13/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 6/13/2022 Approved SEAN HAUPT
Insulation 6/21/2022 Partial Approval MORRIS JACKSON
Shower Pan 6/21/2022 Approved MORRIS JACKSON
Drywall Nailing 6/29/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 6/29/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 8/17/2022 Approved VINCENT HANLEY
Final 8/17/2022 Corrections Issued VINCENT HANLEY
Green Building Final 8/17/2022 Approved VINCENT HANLEY
Green Building Rough 8/17/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/17/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 8/17/2022 Approved VINCENT HANLEY
Final 8/26/2022 Partial Approval SEAN HAUPT