465 S HOLT AVE 90048
Certificate Information: 465 S HOLT AVE 90048
- Application / Permit
- 21014-30000-02523
- Plan Check / Job No.
- B21WL02217
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition to (e) single story SFD (1,031 sf) to add 2 bedrooms, 2 full bathrooms, one 1/2 bathroom
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- CofO Issued on 12/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | REZA HAGHIGHAT |
| Corrections Issued | 6/21/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 6/29/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 10/15/2021 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 10/27/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 11/3/2021 | REZA HAGHIGHAT |
| Issued | 11/3/2021 | APPLICANT |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| CofO in Progress | 11/29/2022 | EVAN COOPER |
| Permit Finaled | 12/27/2022 | DANIEL ORRANTE |
| CofO Issued | 12/27/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/27/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/14/2021 | JEANIE LAM |
| CPC | Cleared | 7/19/2021 | DENZEL HENDERSON |
| Low Impact Development | Cleared | 9/15/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | JEANIE LAM |
Contact Information
| Architect | Youssefzadeh,, Atabak; Lic. No.: C22727 | 438 S PECK DRIVE BEVERLY HILLS, CA 90212 |
| Contractor | Owner-Builder | , |
| Engineer | Mangoli,, Arash; Lic. No.: C84319 | 1727 BENTLEY AVE APT 211 LOS ANGELES, CA 90025 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2021 | Partial Approval | KENNETH NAGLE |
| METHANE-Barrier | 11/19/2021 | Approved | KENNETH NAGLE |
| METHANE-Subgrade | 11/19/2021 | Approved | KENNETH NAGLE |
| Footing/Foundation/Slab | 12/1/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 12/8/2021 | Partial Approval | EVAN COOPER |
| Underground Mechanical | 12/8/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 2/9/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 2/9/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 2/9/2022 | Corrections Issued | EVAN COOPER |
| Wood Frame | 2/9/2022 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 2/15/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 2/15/2022 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 2/15/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 2/15/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 2/15/2022 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 2/15/2022 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 2/25/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 2/25/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 2/25/2022 | Approved | EVAN COOPER |
| Green Building Rough | 2/25/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/25/2022 | Approved | EVAN COOPER |
| METHANE-Rough | 2/25/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 2/25/2022 | Approved | EVAN COOPER |
| Shower Pan | 2/25/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 3/4/2022 | Approved | EVAN COOPER |
| Insulation | 3/4/2022 | Approved | EVAN COOPER |
| Final | 8/12/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 8/12/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 8/12/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/19/2022 | Approved | EVAN COOPER |
| Final | 8/19/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 8/19/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/19/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/19/2022 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 8/19/2022 | Approved | EVAN COOPER |
| Final | 11/28/2022 | OK to Issue CofO | EVAN COOPER |