7865 S VICKSBURG AVE 90045
Certificate Information: 7865 S VICKSBURG AVE 90045
- Application / Permit
- 21014-30000-02482
- Plan Check / Job No.
- B21WL02178
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- Add a utility room (237 sf) to (e) det. garage (362 sf)
- Permit Issued
- Issued on 8/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | REZA HAGHIGHAT |
| Corrections Issued | 6/28/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 7/8/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 12/22/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 5/15/2022 | REZA HAGHIGHAT |
| Building Plans Picked Up | 8/31/2022 | APPLICANT |
| Issued | 8/15/2023 | APPLICANT |
| CofO in Progress | 7/1/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 7/3/2024 | DANIEL ORRANTE |
| CofO Issued | 7/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/4/2021 | PEDRO AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | TRACY TATE |
| Sewer availability | Cleared | 11/9/2021 | TRACY TATE |
| GPI Written Notices | Cleared | 12/22/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 12/22/2021 | REZA HAGHIGHAT |
| Construction near power lines | Cleared | 1/13/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/17/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 4/18/2023 | DINAH GARIN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Mancilla'S Construction Inc; Lic. No.: 1073745-B | 13107 AZTEC ST SYLMAR, CA 91342 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/28/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 8/29/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/29/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 9/19/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/17/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 10/17/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Approved | BOBBY KEY |
| Green Building Rough | 10/17/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 10/17/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/30/2023 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 11/14/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 11/14/2023 | Approved | BOBBY KEY |
| Green Building Rough | 11/14/2023 | Approved | BOBBY KEY |
| Insulation | 11/14/2023 | Approved | BOBBY KEY |
| Service/Power Release | 11/14/2023 | Corrections Issued | BOBBY KEY |
| Service/Power Release | 11/22/2023 | Approved | BOBBY KEY |
| Final | 3/8/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 3/8/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 3/8/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/8/2024 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 3/8/2024 | Approved | JESUS RODRIGUEZ |
| Final | 6/14/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Approved | TEMISTOCLES CAAL |