3951 S SYCAMORE AVE 90008
Certificate Information: 3951 S SYCAMORE AVE 90008
- Application / Permit
- 21014-30000-02476
- Plan Check / Job No.
- B21WL02168
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel Addition to SFD 318sqft and New pouch 32sqft = 350sqft total
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 5/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 5/22/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 6/29/2021 | KHUONG TRUONG |
| Plan Check Approved | 8/3/2021 | KHUONG TRUONG |
| Issued | 1/28/2022 | APPLICANT |
| CofO in Progress | 4/29/2024 | ANTHONY EGSON |
| Permit Finaled | 5/7/2024 | DEROLD HAUFF |
| CofO Issued | 5/7/2024 | DEROLD HAUFF |
| Permit Finaled | 5/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/1/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 6/8/2021 | KIRK LINKLATER |
| Public Works-Highway Ded. | Cleared | 11/17/2023 | RHEA OSORIO |
| Public Works-Open Permits | Cleared | 11/17/2023 | RHEA OSORIO |
| Public Works-Sewers | Cleared | 11/17/2023 | RHEA OSORIO |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/19/2022 | No Access for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 4/26/2022 | Approved | ANTHONY EGSON |
| Insulation | 5/20/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 5/20/2022 | Approved | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 5/24/2022 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/9/2022 | Partial Inspection | ANTHONY EGSON |
| Deputy Wood Construction | 10/14/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/14/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/15/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/21/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 4/21/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 4/27/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/27/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 4/27/2023 | Approved | ANTHONY EGSON |
| Insulation | 5/18/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/24/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/5/2023 | Approved | ANTHONY EGSON |
| Gas Test | 7/25/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 11/6/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/6/2023 | Approved | ANTHONY EGSON |
| Green Building Final | 11/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 11/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 11/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 11/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 11/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 12/18/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 12/18/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 12/18/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/19/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 1/19/2024 | Approved | ANTHONY EGSON |
| Final | 4/26/2024 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 4/26/2024 | Approved | ANTHONY EGSON |
| Smoke Detectors | 4/26/2024 | Approved | ANTHONY EGSON |