16651 W CUMBRE VERDE CT 90272
Certificate Information: 16651 W CUMBRE VERDE CT 90272
- Application / Permit
- 21014-30000-02458
- Plan Check / Job No.
- B21WL02147
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel and covered patio & trellis addition to (E) 2-story SFD
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Current Status
- CofO Issued on 6/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | RICHARD GARCIA |
| Corrections Issued | 5/23/2021 | RICHARD GARCIA |
| Plan Check Approved | 8/9/2021 | JASON JANGADA |
| Issued | 9/23/2022 | APPLICANT |
| Building Plans Picked Up | 9/27/2022 | APPLICANT |
| CofO in Progress | 6/12/2023 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 6/13/2023 | DANIEL ORRANTE |
| CofO Issued | 6/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/21/2021 | BRIAN MILLER |
| Roof/Waste drainage to street | Cleared | 6/22/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | ANTHONY MAINEZ |
| Coastal Zone | Cleared | 7/15/2021 | JOE LUCKEY |
| ZI | Cleared | 7/15/2021 | JOE LUCKEY |
Contact Information
| Contractor | Basix Designs & Remodeling Inc; Lic. No.: 769443-B | 650 S HIGHLAND AVE LOS ANGELES, CA 90036 |
| Engineer | Bayani-Rad,, Padra; Lic. No.: C86320 | 15901 HAWTHORNE BLVD UNIT 220 LAWNDALE, CA 90260 |
Inspector Information
| MICHAEL ALLEN, (310) 914-3886 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/14/2022 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 10/14/2022 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 11/3/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/10/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 1/10/2023 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 1/10/2023 | Partial Approval | BRENDAN LOONEY |
| HVAC-Rough | 1/10/2023 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 1/10/2023 | Partial Approval | BRENDAN LOONEY |
| Drywall Nailing | 1/17/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/16/2023 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 2/16/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/16/2023 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 3/9/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 3/9/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 6/1/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 6/1/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 6/1/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Final | 6/8/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 6/8/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |