1036 N TIGERTAIL ROAD 90049
Certificate Information: 1036 N TIGERTAIL ROAD 90049
- Application / Permit
- 21014-30000-02453
- Plan Check / Job No.
- B21WL02127
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and Addition to (E)xisiting SFD w/attached garage
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Current Status
- CofO Issued on 8/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 6/11/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 6/21/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 11/5/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 12/16/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 1/26/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 1/28/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 3/8/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 4/15/2022 | FELIPE HERNANDEZ |
| Plan Check Approved | 5/13/2022 | FELIPE HERNANDEZ |
| Issued | 6/24/2022 | APPLICANT |
| Building Plans Picked Up | 11/3/2022 | APPLICANT |
| Permit Finaled | 8/4/2025 | RICHARD STEINBACH |
| CofO Issued | 8/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/25/2021 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 7/25/2021 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 7/25/2021 | ANTHONY MAINEZ |
| Highway dedication | Cleared | 7/25/2021 | ANTHONY MAINEZ |
| Permit | Cleared | 7/25/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/25/2021 | ANTHONY MAINEZ |
| Street Frontage | Cleared | 7/25/2021 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 7/27/2021 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 7/27/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2021 | ANTHONY MAINEZ |
| ZA Case | Cleared | 11/5/2021 | NOAH MCCOY |
| Hydrant and Access approval | Cleared | 11/9/2021 | RUEL COLE |
| Low Impact Development | Cleared | 1/3/2022 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 1/13/2022 | STEVEN JIN |
| Trees in Parkway | Cleared | 1/19/2022 | ADALBERTO VERA |
| Grading Pre-Inspection | Cleared | 4/15/2022 | FELIPE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
| Geologist | Nguyen,, An; Lic. No.: EG2468 | 5913 SATURN STREET LOS ANGELES, CA 90035 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/1/2022 | Partial Inspection | MICHAEL PELHAM |
| Deputy Grading | 7/26/2022 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 8/26/2022 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 8/26/2022 | Corrections Issued | MICHAEL PELHAM |
| Piling/Pier/Caisson | 8/29/2022 | Corrections Issued | MICHAEL PELHAM |
| Piling/Pier/Caisson | 8/31/2022 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 9/29/2022 | Partial Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 10/4/2022 | Conditional Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 11/10/2022 | Partial Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 11/30/2022 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 1/26/2023 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/21/2023 | Partial Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/4/2023 | Approved | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 4/20/2023 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/20/2023 | Partial Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 5/15/2023 | No Access for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/15/2023 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 6/15/2023 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/10/2023 | Partial Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 7/28/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/4/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/8/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/14/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/22/2023 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2023 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/11/2023 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 10/11/2023 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 11/9/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/4/2023 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 12/4/2023 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2024 | Approved | CARLOS MATAMOROS |
| Wood Frame | 1/29/2024 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/20/2024 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 5/20/2024 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/20/2024 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/21/2024 | Partial Approval | CARLOS MATAMOROS |
| Insulation | 5/28/2024 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 5/29/2024 | Partial Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 5/29/2024 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/15/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/15/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 7/22/2024 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/1/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 8/1/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/1/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/1/2024 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 8/1/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 8/6/2024 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 10/2/2024 | Approved | CARLOS MATAMOROS |
| Shower Pan | 10/21/2024 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/22/2024 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/27/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 3/17/2025 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 4/16/2025 | Partial Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 5/14/2025 | Approved | CARLOS MATAMOROS |
| Gas Test | 5/14/2025 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 5/15/2025 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 5/19/2025 | Conditional Approval | MICHAEL PELHAM |
| Final | 7/30/2025 | Corrections Issued | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/30/2025 | Approved | MICHAEL PELHAM |
| Green Building Final | 7/30/2025 | Approved | MICHAEL PELHAM |
| HVAC-Final | 7/30/2025 | Approved | MICHAEL PELHAM |
| PLUMBING-Final | 7/30/2025 | Approved | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Not Ready | MICHAEL PELHAM |
| Smoke Detectors | 7/30/2025 | Approved | MICHAEL PELHAM |
| Final | 8/4/2025 | Conditional Approval | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Approved | MICHAEL PELHAM |