1043 N GALLOWAY ST 90272
Certificate Information: 1043 N GALLOWAY ST 90272
- Application / Permit
- 21014-30000-02401
- Plan Check / Job No.
- B21WL02031
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story house addition
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 6/3/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 6/14/2021 | TARIK SAOUD |
| Plan Check Approved | 10/13/2021 | FELIPE HERNANDEZ |
| Issued | 10/28/2021 | APPLICANT |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| CofO in Progress | 11/2/2022 | KEVIN SARGSYAN |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
| CofO Issued | 11/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 6/21/2021 | DENNIS BRAGIN |
| ZA Case | Cleared | 6/24/2021 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2021 | CATHERINE ADROVER |
| Sewer availability | Cleared | 8/6/2021 | CATHERINE ADROVER |
| Trees in Parkway | Cleared | 9/9/2021 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 9/30/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | CATHERINE ADROVER |
| Grading Pre-Inspection | Cleared | 10/13/2021 | FELIPE HERNANDEZ |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/17/2021 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 12/20/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 1/11/2022 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 1/27/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 2/24/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 3/17/2022 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 3/25/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 3/25/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 4/5/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Shower Pan | 4/7/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 4/11/2022 | No Access for Inspection | JOHN KIDWELL |
| Shower Pan | 4/13/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/14/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 4/14/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/20/2022 | Approved | ANDREW NAVE |
| Green Building Rough | 4/20/2022 | Approved | ANDREW NAVE |
| Insulation | 5/2/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 5/12/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/16/2022 | Approved | RYAN SALAZAR |
| Gas Test | 9/20/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 9/20/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 9/20/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 9/21/2022 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 9/27/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 9/27/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 9/27/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/6/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 10/11/2022 | Corrections Issued | ANDREW NAVE |
| Gas Test | 10/11/2022 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Final | 10/11/2022 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 10/11/2022 | Corrections Issued | ANDREW NAVE |
| Final | 10/17/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 10/17/2022 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 10/17/2022 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 10/17/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/25/2022 | Approved | KEVIN SARGSYAN |
| Final | 10/25/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 11/1/2022 | OK to Issue CofO | KEVIN SARGSYAN |