3771 N LONGVIEW VALLEY ROAD 91423
Certificate Information: 3771 N LONGVIEW VALLEY ROAD 91423
- Application / Permit
- 21014-30000-02353
- Plan Check / Job No.
- B21WL02003
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED AND ADDITION OF 102SQFT TO (E) KITCHEN
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- CofO Issued on 10/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2021 | KHUONG TRUONG |
| Corrections Issued | 5/13/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 6/17/2021 | RICHARD GARCIA |
| Plan Check Approved | 7/7/2021 | KHUONG TRUONG |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 10/25/2021 | MISAEL ESPARZA |
| CofO Issued | 10/26/2021 | MICHAEL SMITH |
| Permit Finaled | 10/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/4/2021 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 7/7/2021 | KHUONG TRUONG |
| Grading Pre-Inspection | Cleared | 7/7/2021 | KHUONG TRUONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/2/2021 | Approved | CHARLES POWELL |
| Wood Frame | 8/4/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 8/26/2021 | Approved | CHARLES POWELL |
| Rough-Elec/Plmb/HVAC | 8/26/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 8/30/2021 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/30/2021 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 8/30/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/30/2021 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 9/1/2021 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/22/2021 | Approved | MISAEL ESPARZA |
| Final | 10/22/2021 | OK to Issue CofO | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/22/2021 | Approved | MISAEL ESPARZA |
| Green Building Final | 10/22/2021 | Approved | MISAEL ESPARZA |
| HVAC-Final | 10/22/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 10/22/2021 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/22/2021 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 10/22/2021 | Approved | MISAEL ESPARZA |