17063 W SIGNATURE DR 91344

Certificate Information: 17063 W SIGNATURE DR 91344

Application / Permit
21014-30000-02352
Plan Check / Job No.
B21WL01992
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
BEDROOM ADDITION
Permit Issued
Issued on 7/8/2021
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2021 APPLICANT
Assigned to Plan Check Engineer 5/11/2021 KHUONG TRUONG
Corrections Issued 5/11/2021 KHUONG TRUONG
Applicant returned to address corrections 6/4/2021 KHUONG TRUONG
Plan Check Approved 6/28/2021 RICHARD GARCIA
Issued 7/8/2021 APPLICANT
CofO in Progress 1/5/2022 DAVID SCANTLIN
CofO Issued 9/10/2022 DANIEL ORRANTE
Permit Finaled 9/10/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/15/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/15/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/15/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Brauner Construction & Realty; Lic. No.: 1051764-B 3734 S CANFIELD AVE APT 228      LOS ANGELES, CA 90034
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/26/2021 Conditional Approval KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 7/27/2021 Approved DAVID SCANTLIN
ELECTRICAL-Rough 8/27/2021 Approved DAVID SCANTLIN
Wood Frame 8/27/2021 Approved DAVID SCANTLIN
Insulation 9/7/2021 Corrections Issued DEANDRE HOFFMAN
Drywall Nailing 9/13/2021 Approved RYAN SALAZAR
Insulation 9/13/2021 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/20/2021 Approved DAVID SCANTLIN
ELECTRICAL-Final 9/20/2021 Not Ready for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 9/20/2021 Approved DAVID SCANTLIN
Green Building Final 9/20/2021 Approved DAVID SCANTLIN
Green Building Rough 9/20/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 9/20/2021 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 9/20/2021 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 9/20/2021 Approved DAVID SCANTLIN
ELECTRICAL-Final 9/23/2021 Approved DAVID SCANTLIN
Final 1/4/2022 OK to Issue CofO DAVID SCANTLIN