5646 N LUBAO AVE 91367
Certificate Information: 5646 N LUBAO AVE 91367
- Application / Permit
- 21014-30000-02164
- Plan Check / Job No.
- B21WL01875
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) SFD
- Permit Issued
- Issued on 3/21/2022
- Issuing Office
- Current Status
- CofO Issued on 12/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2021 | JASON JANGADA |
| Corrections Issued | 5/3/2021 | JASON JANGADA |
| Applicant returned to address corrections | 5/13/2021 | JASON JANGADA |
| Applicant returned to address corrections | 6/4/2021 | ALFREDO JARA |
| Plan Check Approved | 1/28/2022 | ALFREDO JARA |
| Issued | 3/21/2022 | APPLICANT |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| CofO in Progress | 10/28/2022 | SEAN HAUPT |
| Permit Finaled | 12/9/2022 | MICHAEL SMITH |
| CofO Issued | 12/9/2022 | MICHAEL SMITH |
| Permit Finaled | 12/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/18/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 12/22/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/13/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Potato Construction Inc; Lic. No.: 1003152-B | 735 W DUARTE RD SUITE #301 ARCADIA, CA 91007 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/30/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 4/13/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 4/13/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 7/14/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 8/2/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 8/17/2022 | Partial Approval | MORRIS JACKSON |
| Insulation | 8/26/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 9/7/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/5/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 10/5/2022 | Approved | SEAN HAUPT |
| Final | 10/5/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 10/5/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 10/5/2022 | Approved | SEAN HAUPT |
| MERV13>=Final | 10/5/2022 | Approved | SEAN HAUPT |
| MERV13>=Rough | 10/5/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 10/5/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 10/5/2022 | Approved | SEAN HAUPT |
| Final | 10/27/2022 | OK to Issue CofO | SEAN HAUPT |