6932 W 85TH ST 90045
Certificate Information: 6932 W 85TH ST 90045
- Application / Permit
- 21014-30000-02151
- Plan Check / Job No.
- B21WL01867
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel & addition to (E) SFD.
- Permit Issued
- Issued on 1/13/2022
- Issuing Office
- Current Status
- CofO Issued on 5/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 5/4/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 8/26/2021 | JASON JANGADA |
| Applicant returned to address corrections | 9/23/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 10/5/2021 | KHUONG TRUONG |
| Issued | 1/13/2022 | APPLICANT |
| Building Plans Picked Up | 1/5/2023 | APPLICANT |
| CofO in Progress | 5/24/2023 | BOBBY KEY |
| Permit Finaled | 5/30/2023 | DANIEL ORRANTE |
| CofO Issued | 5/30/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/30/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/17/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | DINAH GARIN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Dave'S Works Corporation; Lic. No.: 788467-B | 6227 WEST 87TH STREET LOS ANGELES, CA 90045 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/2/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Pre-Inspection | 5/2/2022 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/9/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/21/2022 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 6/21/2022 | Not Ready for Inspection | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Conditional Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 9/26/2022 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 1/3/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 1/3/2023 | Approved | BOBBY KEY |
| Green Building Rough | 1/3/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 1/5/2023 | Approved | BOBBY KEY |
| Deputy Drilled-In Anchors | 1/5/2023 | Approved | BOBBY KEY |
| Final | 1/5/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2023 | Approved | BOBBY KEY |
| Green Building Rough | 1/5/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 1/5/2023 | Approved | BOBBY KEY |
| Insulation | 1/17/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 1/25/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/19/2023 | Approved | BOBBY KEY |
| Final | 5/19/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 5/19/2023 | Approved | BOBBY KEY |
| HVAC-Final | 5/19/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/19/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/19/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 5/19/2023 | Approved | BOBBY KEY |
| Final | 5/24/2023 | OK to Issue CofO | BOBBY KEY |