6932 W 85TH ST 90045

Certificate Information: 6932 W 85TH ST 90045

Application / Permit
21014-30000-02151
Plan Check / Job No.
B21WL01867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel & addition to (E) SFD.
Permit Issued
Issued on 1/13/2022
Issuing Office
Current Status
CofO Issued on 5/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 4/30/2021 JAHANSHAH POURHASSAN
Corrections Issued 5/4/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 8/26/2021 JASON JANGADA
Applicant returned to address corrections 9/23/2021 JAHANSHAH POURHASSAN
Plan Check Approved 10/5/2021 KHUONG TRUONG
Issued 1/13/2022 APPLICANT
Building Plans Picked Up 1/5/2023 APPLICANT
CofO in Progress 5/24/2023 BOBBY KEY
Permit Finaled 5/30/2023 DANIEL ORRANTE
CofO Issued 5/30/2023 DANIEL ORRANTE
Permit Finaled 5/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/17/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/18/2021 DINAH GARIN

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Dave'S Works Corporation; Lic. No.: 788467-B 6227 WEST 87TH STREET      LOS ANGELES, CA 90045

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/2/2022 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 5/2/2022 Conditional Approval JESUS RODRIGUEZ
Pre-Inspection 5/2/2022 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 5/9/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 5/9/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 6/21/2022 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Corrections Issued BOBBY KEY
Green Building Rough 6/21/2022 Not Ready for Inspection BOBBY KEY
Excavation/Setback/Form/Re-Bar 8/10/2022 Conditional Approval HERBERT GIRON
Interior/Exterior Lathing 9/26/2022 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 1/3/2023 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 1/3/2023 Approved BOBBY KEY
Green Building Rough 1/3/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 1/5/2023 Approved BOBBY KEY
Deputy Drilled-In Anchors 1/5/2023 Approved BOBBY KEY
Final 1/5/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/5/2023 Approved BOBBY KEY
Green Building Rough 1/5/2023 Approved BOBBY KEY
HVAC-Rough 1/5/2023 Approved BOBBY KEY
Insulation 1/17/2023 Approved BOBBY KEY
Drywall Nailing 1/25/2023 Approved BOBBY KEY
ELECTRICAL-Final 5/19/2023 Approved BOBBY KEY
Final 5/19/2023 Corrections Issued BOBBY KEY
Green Building Final 5/19/2023 Approved BOBBY KEY
HVAC-Final 5/19/2023 Approved BOBBY KEY
PLUMBING-Final 5/19/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/19/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 5/19/2023 Approved BOBBY KEY
Final 5/24/2023 OK to Issue CofO BOBBY KEY