5415 N NAGLE AVE 91401

Certificate Information: 5415 N NAGLE AVE 91401

Application / Permit
21014-30000-02117
Plan Check / Job No.
B21WL01832
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior Remodel of (E) 2-Story S.F.D, Footprint to remain No Additional Square Footage, No Change to all (E) Setbacks. Replace Pitched Roof over 1st Floor with Flat Roof. Pitched Roof over Second Floor to Remain (No Change), Insulate Entire House to Current Title 24 Requirements. Replace all (E) Windows ans Doors with New Energy Efficient Door and Windows
Permit Issued
Issued on 8/28/2021
Issuing Office
Current Status
Permit Finaled on 7/14/2023

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 5/12/2021 DAVID CASTILLO
Corrections Issued 5/18/2021 DAVID CASTILLO
Quality Review Completed 6/2/2021 TARIK SAOUD
Applicant returned to address corrections 6/22/2021 DAVID CASTILLO
Plan Check Approved 7/9/2021 DAVID CASTILLO
Issued 8/28/2021 APPLICANT
Permit Finaled 7/13/2023 RYAN SALAZAR

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/21/2021 LEE GUILBEAUX
Sewer availability Cleared 6/21/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/21/2021 LEE GUILBEAUX

Contact Information

Contractor Bel Air Builders Inc; Lic. No.: 872640-B 17220 SUNBURST STREET      NORTHRIDGE, CA 91325
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2021 Approved AMY COLIN
Deputy Wood Construction 1/27/2022 Conditional Approval ALAN MORELOS
ELECTRICAL-Rough 1/28/2022 Approved RICHARD DOCKUS
HVAC-Rough 1/28/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 1/28/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 2/18/2022 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 2/25/2022 Partial Approval RICHARD DOCKUS
Wood Frame 2/25/2022 Partial Approval RICHARD DOCKUS
Wood Frame 3/21/2022 Corrections Issued RICHARD DOCKUS
Deputy Drilled-In Anchors 3/30/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 4/5/2022 Corrections Issued RICHARD DOCKUS
Deputy Reinf. Concrete 4/6/2022 Approved RICHARD DOCKUS
Deputy Steel/Welding 4/15/2022 Approved RICHARD DOCKUS
Insulation 5/23/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 5/23/2022 Partial Approval ALAN MORELOS
Insulation 5/25/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 5/25/2022 Partial Approval ALAN MORELOS
Drywall Nailing 6/8/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 9/22/2022 Approved WILLIAM WREN
Shower Pan 9/22/2022 Approved WILLIAM WREN
Grounding or Bonding 6/13/2023 Partial Approval RYAN SALAZAR
Enclosure/Fence 7/3/2023 Approved RYAN SALAZAR
Final 7/13/2023 Permit Finaled RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 7/13/2023 Approved RYAN SALAZAR