9307 W BOLTON ROAD 90034
Certificate Information: 9307 W BOLTON ROAD 90034
- Application / Permit
- 21014-30000-02086
- Plan Check / Job No.
- B21WL01815
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY SFD W./ ATT/ 2-CAR GARAGE AND ATT. ADU PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 8/30/2021
- Issuing Office
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2021 | HOOMAN HAJIZADEH |
| Corrections Issued | 5/18/2021 | HOOMAN HAJIZADEH |
| Quality Review Completed | 6/1/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 8/18/2021 | HOOMAN HAJIZADEH |
| Plan Check Approved | 8/25/2021 | HOOMAN HAJIZADEH |
| Issued | 8/30/2021 | APPLICANT |
| CofO in Progress | 8/31/2022 | OGANES TARAKHCHYAN |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2021 | DENNIS BRAGIN |
| Permit | Cleared | 6/17/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 6/19/2021 | DENNIS BRAGIN |
| Trees in Parkway | Cleared | 7/1/2021 | JOHN KIM |
| Low Impact Development | Cleared | 8/3/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/3/2021 | DENNIS BRAGIN |
| Miscellaneous | Cleared | 8/6/2021 | LOUIS ORTEGA |
| GPI Written Notices | Cleared | 8/19/2021 | HOOMAN HAJIZADEH |
| Grading Pre-Inspection | Cleared | 8/19/2021 | HOOMAN HAJIZADEH |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Arriola,, Kirby Norman; Lic. No.: C31416 | PO BOX 5566 OXNARD, CA 93031 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/23/2021 | Partial Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 11/1/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 11/1/2021 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 11/3/2021 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 11/16/2021 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 12/6/2021 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 12/10/2021 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Deputy Wood Construction | 2/11/2022 | Conditional Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 2/25/2022 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 2/25/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/2/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/2/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/14/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/14/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 3/18/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 3/18/2022 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Final | 3/18/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 3/18/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/18/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/23/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/23/2022 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 3/23/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/23/2022 | Approved | EVAN COOPER |
| Insulation | 4/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 4/7/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 4/11/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/22/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 5/5/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 8/2/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/18/2022 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 8/18/2022 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 8/22/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Green Building Final | 8/25/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/25/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 8/30/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |