5321 W FRANKLIN AVE 90027
Certificate Information: 5321 W FRANKLIN AVE 90027
- Application / Permit
- 21014-30000-02041
- Plan Check / Job No.
- B21WL01779
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and Addition to existing SFD (2-story w/ att. garage)
- Permit Issued
- Issued on 2/6/2022
- Issuing Office
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 6/3/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 6/14/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 9/23/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 10/19/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 1/7/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 1/10/2022 | FELIPE HERNANDEZ |
| Plan Check Approved | 2/1/2022 | FELIPE HERNANDEZ |
| Issued | 2/6/2022 | APPLICANT |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| CofO in Progress | 8/22/2024 | ROY SPAULDING |
| CofO in Progress | 10/18/2024 | CRAIG VAUGHAN |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
| CofO Issued | 11/1/2024 | DEROLD HAUFF |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/17/2021 | JASON HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 6/22/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 6/22/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 6/22/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 6/22/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 6/22/2021 | WALLIE JONG |
| Highway dedication | Cleared | 6/22/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/22/2021 | WALLIE JONG |
| Sewer availability | Cleared | 6/22/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | WALLIE JONG |
| Watercourse | Cleared | 9/16/2021 | SAM NAVID |
| Permit | Cleared | 11/1/2021 | WALLIE JONG |
| Trees in Parkway | Cleared | 11/17/2021 | ADALBERTO VERA |
| ZA Case | Cleared | 12/28/2021 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 1/20/2022 | ANTHONY VARGAS |
Contact Information
| Architect | Williger,, Paul Brant; Lic. No.: C24022 | 26176 FAIRSIDE ROAD MALIBU, CA 90265 |
| Contractor | B T C Builders Inc; Lic. No.: 743191-B | 11373 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
| Landscape Architect | Fields,, Cheryl; Lic. No.: LA5386 | 336 N AZUSA AVE APT A AZUSA, CA 91702 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2022 | Approved | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 4/13/2022 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 4/18/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/8/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 6/20/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 7/15/2022 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 7/21/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/26/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/1/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/16/2022 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 8/16/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 8/16/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/23/2022 | Approved | SCOTT FINNILA |
| Special/Order Compliance | 9/12/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 9/15/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 9/15/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 9/26/2022 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 10/12/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/18/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Gas Test | 7/14/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 1/16/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 2/28/2024 | Approved | ROY SPAULDING |
| PLUMBING-Final | 5/8/2024 | Approved | ROY SPAULDING |
| Final | 5/22/2024 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 5/22/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 5/22/2024 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 7/23/2024 | Approved | ROY SPAULDING |
| Final | 7/30/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 8/6/2024 | OK to Issue CofO | ROY SPAULDING |
| Final | 9/16/2024 | Corrections Issued | CRAIG VAUGHAN |
| Final | 10/17/2024 | OK to Issue CofO | CRAIG VAUGHAN |