825 N NORMAN PL 90049
Certificate Information: 825 N NORMAN PL 90049
- Application / Permit
- 21014-30000-02008
- Plan Check / Job No.
- B21WL01761
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and alteration to (E) SFD w/ (N) 3-car garage and roof trusses, Equipped w/ Fire sprinklers NFPA 13D.
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 2/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | ALFREDO JARA |
| Corrections Issued | 5/6/2021 | ALFREDO JARA |
| Quality Review Completed | 5/12/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/25/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 10/4/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 10/12/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 10/20/2021 | ALFREDO JARA |
| Plan Check Approved | 10/25/2021 | ALFREDO JARA |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| CofO in Progress | 2/23/2023 | CARLOS MATAMOROS |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
| CofO Issued | 2/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 5/20/2021 | JOHN KIM |
| BHO/Hillside ordinance | Cleared | 6/9/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 6/9/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 6/9/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 6/9/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 6/9/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | DENNIS BRAGIN |
| Permit | Cleared | 6/9/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 6/9/2021 | DENNIS BRAGIN |
| Watercourse | Cleared | 6/9/2021 | DENNIS BRAGIN |
| ZA Case | Cleared | 6/14/2021 | KENTON TRINH |
| Low Impact Development | Cleared | 8/4/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 8/5/2021 | DENNIS BRAGIN |
| Green Code | Cleared | 8/25/2021 | ALFREDO JARA |
| Hydrant and Access approval | Cleared | 9/22/2021 | ROBERT DUFF |
| GPI Written Notices | Cleared | 10/25/2021 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 10/25/2021 | ALFREDO JARA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/18/2022 | Partial Inspection | MICHAEL PELHAM |
| PLUMBING-Rough | 2/8/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 3/3/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/7/2022 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/11/2022 | Approved | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 3/29/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Conditional Approval | CARLOS MATAMOROS |
| Green Building Rough | 3/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 3/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Wood Construction | 3/30/2022 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 4/4/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Wood Construction | 4/27/2022 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 4/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 4/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 4/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/24/2022 | Approved | CARLOS MATAMOROS |
| Gas Test | 5/26/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/26/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 5/31/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 6/2/2022 | Corrections Issued | DANIEL ORRANTE |
| Shower Pan | 6/2/2022 | Approved | DANIEL ORRANTE |
| HVAC-Rough | 6/6/2022 | Approved | BRENDAN LOONEY |
| Shower Pan | 6/8/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 6/15/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 6/15/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 6/15/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/21/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 6/21/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 6/21/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 6/29/2022 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 7/14/2022 | Approved | CARLOS MATAMOROS |
| Insulation | 7/14/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/8/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 9/12/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/6/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 10/6/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 10/12/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 10/12/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 11/1/2022 | Corrections Issued | CARLOS MATAMOROS |
| Service/Power Release | 11/4/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 11/18/2022 | Approved | CARLOS MATAMOROS |
| Final | 2/22/2023 | Partial Approval | CARLOS MATAMOROS |
| Green Building Final | 2/22/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 2/22/2023 | Approved | CARLOS MATAMOROS |
| Final | 2/23/2023 | OK to Issue CofO | CARLOS MATAMOROS |