1650 S VICTORIA AVE 90019

Certificate Information: 1650 S VICTORIA AVE 90019

Application / Permit
21014-30000-01969
Plan Check / Job No.
B21WL01729
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New garage *** 3 of 3 ***
Permit Issued
Issued on 10/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 RICHARD GARCIA
Corrections Issued 5/2/2021 RICHARD GARCIA
Quality Review Completed 5/12/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/7/2022 RICHARD GARCIA
Applicant returned to address corrections 3/31/2022 RICHARD GARCIA
Applicant returned to address corrections 4/12/2022 RICHARD GARCIA
Applicant returned to address corrections 6/24/2022 RICHARD GARCIA
Applicant returned to address corrections 7/19/2022 RICHARD GARCIA
Plan Check Approved 8/4/2022 RICHARD GARCIA
Building Plans Picked Up 10/11/2022 APPLICANT
Issued 10/27/2022 APPLICANT
CofO in Progress 4/23/2024 JUSTIN HAWLEY
CofO in Progress 4/24/2024 JUSTIN HAWLEY
CofO in Progress 10/11/2024 JUSTIN HAWLEY
Permit Finaled 10/25/2024 RUBEN SALAS
CofO Issued 10/25/2024 RUBEN SALAS
Permit Finaled 10/25/2024 RUBEN SALAS

Permit Application Clearance Information

HPOZ Cleared 7/13/2021 AMANDA KAINER
Eng Process Fee Ord 176,300 Cleared 7/26/2021 WALLIE JONG
ZI Cleared 2/8/2022 AMANDA KAINER
Roof/Waste drainage to street Cleared 2/9/2022 WALLIE JONG

Contact Information

Contractor Level Frame Construction Inc; Lic. No.: 1078493-B 1834 W 84TH PL      LOS ANGELES, CA 90047
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2022 Partial Approval STUART CHAPMAN
Sewer 11/30/2022 Approved MICHAEL LEWIS
Underground Mechanical 11/30/2022 Approved MICHAEL LEWIS
Footing/Foundation/Slab 12/6/2022 Corrections Issued STUART CHAPMAN
METHANE-Barrier 12/6/2022 Approved STUART CHAPMAN
METHANE-Subgrade 12/6/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 1/10/2023 Not Ready for Inspection CALEB MEISTER
Green Building Rough 1/10/2023 Approved CALEB MEISTER
METHANE-Rough 1/10/2023 Not Ready for Inspection CALEB MEISTER
Wood Frame 2/7/2023 Corrections Issued CALEB MEISTER
ELECTRICAL-Rough 2/28/2023 Not Ready for Inspection CALEB MEISTER
Underground Mechanical 2/28/2023 Not Ready for Inspection CALEB MEISTER
Deputy Wood Construction 3/14/2023 Conditional Approval CALEB MEISTER
ELECTRICAL-Rough 3/22/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 3/22/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 3/22/2023 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 4/11/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 12/22/2023 Not Ready for Inspection JUSTIN HAWLEY
Final 12/22/2023 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 12/22/2023 Not Ready for Inspection JUSTIN HAWLEY
Green Building Final 12/22/2023 Not Ready for Inspection JUSTIN HAWLEY
METHANE-Final 12/22/2023 Not Ready for Inspection JUSTIN HAWLEY
METHANE-Rough 12/22/2023 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Not Ready JUSTIN HAWLEY
Service/Power Release 12/22/2023 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 12/22/2023 Not Ready for Inspection JUSTIN HAWLEY
BUILDING-Rough-Frame 1/2/2024 Not Ready for Inspection JUSTIN HAWLEY
Final 1/2/2024 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 1/2/2024 Not Ready for Inspection JUSTIN HAWLEY
Green Building Final 1/2/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 1/2/2024 SGSOV Not Ready JUSTIN HAWLEY
Service/Power Release 1/2/2024 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 1/2/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 4/23/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 4/23/2024 Approved JUSTIN HAWLEY
Final 4/23/2024 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 4/23/2024 Approved JUSTIN HAWLEY
HVAC-Final 4/23/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 4/23/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 4/23/2024 SGSOV Approved JUSTIN HAWLEY
Service/Power Release 4/23/2024 Approved JUSTIN HAWLEY
Final 4/24/2024 Corrections Issued JUSTIN HAWLEY
Final 10/11/2024 OK to Issue CofO JUSTIN HAWLEY