1355 N BOBOLINK PL 90069

Certificate Information: 1355 N BOBOLINK PL 90069

Application / Permit
21014-30000-01967
Plan Check / Job No.
B21WL01715
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF EXISTING CRAWLSPACE INTO A REC-ROOM (175 SF) "COMPLY WITH DEPARTMENT ORDER effective date 02/15/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 6/17/2021
Issuing Office
Current Status
CofO Issued on 4/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 KAVIAN REFAHI
Corrections Issued 4/24/2021 KAVIAN REFAHI
Plan Check Approved 5/12/2021 REZA HAGHIGHAT
Issued 6/17/2021 APPLICANT
CofO in Progress 3/8/2022 GORDON ZUBER
Permit Finaled 4/18/2022 DANIEL SANCHEZ
CofO Issued 4/18/2022 DANIEL SANCHEZ
Permit Finaled 4/18/2022 DANIEL SANCHEZ

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/12/2021 KAVIAN REFAHI

Contact Information

Contractor Readymen Construction Inc; Lic. No.: 578917-B PO BOX 7339      TORRANCE, CA 90504
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/24/2021 Approved JOEL WILLIAMS
Footing/Foundation/Slab 8/25/2021 Partial Inspection GORDON ZUBER
Footing/Foundation/Slab 9/1/2021 Approved GORDON ZUBER
BUILDING-Rough-Frame 10/5/2021 Approved GORDON ZUBER
ELECTRICAL-Rough 10/5/2021 Approved GORDON ZUBER
Green Building Rough 10/5/2021 Approved GORDON ZUBER
Insulation 10/12/2021 Not Ready for Inspection GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 10/25/2021 Corrections Issued GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Approved GORDON ZUBER
HVAC-Rough 11/3/2021 Approved GORDON ZUBER
Drywall Nailing 1/28/2022 Approved ZEYDI STEWART
Special/Order Compliance 1/28/2022 Partial Inspection PIERRE VEGA
Final 2/18/2022 Conditional Approval GORDON ZUBER
Green Building Final 2/18/2022 Approved GORDON ZUBER
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Approved GORDON ZUBER
Smoke Detectors 2/18/2022 Approved GORDON ZUBER