6230 W DEL VALLE DR 90048

Certificate Information: 6230 W DEL VALLE DR 90048

Application / Permit
21014-30000-01946
Plan Check / Job No.
B21WL01693
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
21'3"X13'10" 1ST FLOOR REAR ADDITION AND REMODEL OF (E) SFD.
Permit Issued
Issued on 4/20/2022
Issuing Office
Current Status
CofO Issued on 10/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 MARVEL DELACRUZ
Corrections Issued 5/30/2021 MARVEL DELACRUZ
Quality Review Completed 6/4/2021 STEVEN KIM
Building Plans Picked Up 6/15/2021 APPLICANT
Applicant returned to address corrections 8/20/2021 MARVEL DELACRUZ
Applicant returned to address corrections 10/8/2021 MARVEL DELACRUZ
Plan Check Approved 12/16/2021 MARVEL DELACRUZ
Issued 4/20/2022 APPLICANT
CofO in Progress 10/11/2023 DAVID FEILER
Permit Finaled 10/14/2023 DEROLD HAUFF
CofO Issued 10/14/2023 DEROLD HAUFF
Permit Finaled 10/14/2023 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 8/3/2021 LAMBERT GIESSINGER
Hist. Property Cntrct Mgr Appr Cleared 8/3/2021 LAMBERT GIESSINGER
Historic monument Cleared 8/3/2021 LAMBERT GIESSINGER
ZI Cleared 8/3/2021 LAMBERT GIESSINGER
Eng Process Fee Ord 176,300 Cleared 8/9/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 8/9/2021 JEANIE LAM
Sewer availability Cleared 8/10/2021 JEANIE LAM
Green Code Cleared 12/16/2021 MARVEL DELACRUZ

Contact Information

Architect Schoeplein,, Marc; Lic. No.: C24842 960 BLUEGRASS WAY      LOS ANGELES, CA 90049
Contractor C R L Construction Inc; Lic. No.: 939761-B 13844 VENTURA BLVD #100      SHERMAN OAKS, CA 91423
Engineer Martinez,, Michael Anthony; Lic. No.: S3825 902 15TH PLACE      HERMOSA BEACH, CA 90254

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/24/2022 Conditional Approval ADAM ESCOTO
Deputy Drilled-In Anchors 7/6/2022 Conditional Approval ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 7/15/2022 Corrections Issued ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 9/13/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 12/6/2022 Approved MICHAEL LEWIS
HVAC-Rough 12/6/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 12/6/2022 Conditional Approval MICHAEL LEWIS
BUILDING-Rough-Frame 1/5/2023 Partial Approval RICHARD DOCKUS
Green Building Rough 1/5/2023 Not Ready for Inspection RICHARD DOCKUS
METHANE-Rough 1/5/2023 Partial Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 1/10/2023 No Access for Inspection ALIZAH MAYAGOITIA
Green Building Rough 1/10/2023 No Access for Inspection ALIZAH MAYAGOITIA
METHANE-Rough 1/10/2023 No Access for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/23/2023 Partial Approval RICHARD DOCKUS
Green Building Rough 1/23/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 1/31/2023 Approved SCOTT FINNILA
Green Building Rough 1/31/2023 Approved SCOTT FINNILA
Insulation 1/31/2023 Conditional Approval SCOTT FINNILA
METHANE-Rough 1/31/2023 Approved SCOTT FINNILA
PLUMBING-Rough 1/31/2023 Approved SCOTT FINNILA
Drywall Nailing 2/7/2023 Approved RICHARD DOCKUS
Shower Pan 2/7/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 2/10/2023 Approved MICHAEL LEWIS
Deputy Drilled-In Anchors 4/3/2023 Conditional Approval MICHAEL LEWIS
Final 8/23/2023 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 8/23/2023 Approved ROY SPAULDING
Green Building Final 8/23/2023 Approved ROY SPAULDING
METHANE-Barrier 8/23/2023 Approved ROY SPAULDING
METHANE-Subgrade 8/23/2023 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Approved ROY SPAULDING
Smoke Detectors 8/23/2023 Approved ROY SPAULDING
Final 10/6/2023 OK to Issue CofO ROY SPAULDING