3958 S MICHAEL AVE 90066
Certificate Information: 3958 S MICHAEL AVE 90066
- Application / Permit
- 21014-30000-01935
- Plan Check / Job No.
- B21WL01688
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE AND RELOCATE (E) ENTRY ROOF, DOOR AND STEPS AT FRONT OF (E) SFD, REMODEL MASTER BATHROOM, HALLWAY BATHROOM AND KITCHEN, RECONFIGURE LAUNDRY.
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 6/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 4/22/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 6/11/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 6/14/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 6/22/2021 | ALFREDO JARA |
| Plan Check Approved | 7/7/2021 | KHUONG TRUONG |
| Issued | 7/22/2021 | APPLICANT |
| CofO in Progress | 6/14/2025 | DAVID FEILER |
| Permit Finaled | 6/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/20/2025 | RICHARD STEINBACH |
| CofO Issued | 6/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/6/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Schevers Construction Llc; Lic. No.: 802078-B | 7731 BOEING AVE LOS ANGELES, CA 90045 |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/3/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/3/2021 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/19/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/19/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/19/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/20/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 8/20/2021 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/20/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/24/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 8/24/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/2/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/16/2021 | Approved | DEANDRE HOFFMAN |
| HVAC-Rough | 11/16/2021 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Rough | 11/16/2021 | Approved | DEANDRE HOFFMAN |
| Insulation | 11/19/2021 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/19/2021 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 11/19/2021 | Approved | STEPHANIE SWANSON |
| Insulation | 11/22/2021 | Approved | JOHN KAYON |
| Drywall Nailing | 12/14/2021 | Approved | JOHN KAYON |
| ELECTRICAL-Final | 3/3/2022 | Approved | ENRIQUE MIRELES |
| Final | 3/3/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/3/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 3/3/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 3/3/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/3/2022 | Approved | ENRIQUE MIRELES |
| Final | 6/14/2025 | OK to Issue CofO | DAVID FEILER |