REMOVE AND RELOCATE (E) ENTRY ROOF, DOOR AND STEPS AT FRONT OF (E) SFD, REMODEL MASTER BATHROOM, HALLWAY BATHROOM AND KITCHEN, RECONFIGURE LAUNDRY.
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 6/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2021 APPLICANT
Assigned to Plan Check Engineer 4/20/2021 JAHANSHAH POURHASSAN
Corrections Issued 4/22/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/11/2021 ALFREDO JARA
Applicant returned to address corrections 6/14/2021 ALFREDO JARA
Applicant returned to address corrections 6/22/2021 ALFREDO JARA
Plan Check Approved 7/7/2021 KHUONG TRUONG
Issued 7/22/2021 APPLICANT
CofO in Progress 6/14/2025 DAVID FEILER
Permit Finaled 6/20/2025 RICHARD STEINBACH
Permit Finaled 6/20/2025 RICHARD STEINBACH
CofO Issued 6/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/6/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 5/11/2021 HISASHI KOBAYAKAWA

Contact Information

Contractor Schevers Construction Llc; Lic. No.: 802078-B 7731 BOEING AVE      LOS ANGELES, CA 90045
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/3/2021 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 8/3/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/19/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 8/19/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 8/19/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 8/20/2021 Approved ENRIQUE MIRELES
HVAC-Rough 8/20/2021 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 8/20/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/24/2021 Approved ENRIQUE MIRELES
HVAC-Rough 8/24/2021 Approved ENRIQUE MIRELES
Drywall Nailing 9/2/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/16/2021 Approved DEANDRE HOFFMAN
HVAC-Rough 11/16/2021 Approved DEANDRE HOFFMAN
PLUMBING-Rough 11/16/2021 Approved DEANDRE HOFFMAN
Insulation 11/19/2021 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 11/19/2021 Partial Approval STEPHANIE SWANSON
Shower Pan 11/19/2021 Approved STEPHANIE SWANSON
Insulation 11/22/2021 Approved JOHN KAYON
Drywall Nailing 12/14/2021 Approved JOHN KAYON
ELECTRICAL-Final 3/3/2022 Approved ENRIQUE MIRELES
Final 3/3/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 3/3/2022 Approved ENRIQUE MIRELES
HVAC-Final 3/3/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 3/3/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 3/3/2022 Approved ENRIQUE MIRELES
Final 6/14/2025 OK to Issue CofO DAVID FEILER