6352 W MARYLAND DR 90048

Certificate Information: 6352 W MARYLAND DR 90048

Application / Permit
21014-30000-01857
Plan Check / Job No.
B21WL01618
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Covert (e) garage to ADU with addition per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 5/11/2022
Issuing Office
Current Status
CofO Issued on 10/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2021 APPLICANT
Assigned to Plan Check Engineer 4/21/2021 MARJAN SHENASI
Corrections Issued 4/24/2021 MARJAN SHENASI
Applicant returned to address corrections 6/28/2021 JASON JANGADA
Applicant returned to address corrections 7/18/2021 JASON JANGADA
Applicant returned to address corrections 8/3/2021 MANUEL GARCIA
Applicant returned to address corrections 8/17/2021 ALFREDO JARA
Applicant returned to address corrections 8/26/2021 ALFREDO JARA
Applicant returned to address corrections 2/1/2022 ALFREDO JARA
Applicant returned to address corrections 2/2/2022 ALFREDO JARA
Building Plans Picked Up 2/2/2022 APPLICANT
Applicant returned to address corrections 2/24/2022 ALFREDO JARA
Plan Check Approved 3/22/2022 ALFREDO JARA
Issued 5/11/2022 APPLICANT
CofO in Progress 9/24/2024 ARAM AVEDISIAN
Permit Finaled 10/15/2024 RICHARD STEINBACH
CofO Issued 10/15/2024 RICHARD STEINBACH
Permit Finaled 10/15/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/7/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 5/7/2021 WALLIE JONG
CPC Cleared 5/10/2021 KENTON TRINH
ZI Cleared 5/10/2021 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 5/11/2021 WALLIE JONG
Sewer availability Cleared 5/11/2021 WALLIE JONG
Construction within easement Cleared 6/2/2021 WALTER RAMIREZ
Hydrant and Access approval Cleared 6/17/2021 MATTHEW CRAIG
Low Impact Development Cleared 2/10/2022 TA ANH

Contact Information

Contractor Rimon Adam; Lic. No.: 935565-B 554 SAN VICENTE BLVD      LOS ANGELES, CA 90042
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2022 Corrections Issued EVAN COOPER
METHANE-Barrier 5/20/2022 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 5/20/2022 Not Ready for Inspection EVAN COOPER
Underground Mechanical 5/20/2022 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 7/7/2022 Approved EVAN COOPER
PLUMBING-Rough 7/7/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 7/12/2022 Approved EVAN COOPER
METHANE-Barrier 7/12/2022 Approved EVAN COOPER
Underground Mechanical 7/12/2022 Partial Approval EVAN COOPER
Shower Pan 8/24/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 8/26/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/26/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Shower Pan 8/26/2022 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 9/2/2022 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 9/2/2022 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 9/2/2022 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 9/7/2022 Approved EVAN COOPER
Interior/Exterior Lathing 9/7/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 9/9/2022 Approved STEPHANIE SWANSON
Drywall Nailing 9/9/2022 Approved STEPHANIE SWANSON
Green Building Rough 9/9/2022 Approved STEPHANIE SWANSON
METHANE-Rough 9/9/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 10/31/2022 Not Ready for Inspection EVAN COOPER
Green Building Final 10/31/2022 Not Ready for Inspection EVAN COOPER
HVAC-Final 10/31/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 10/31/2022 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Approved EVAN COOPER
Service/Power Release 10/31/2022 Approved EVAN COOPER
Smoke Detectors 10/31/2022 Not Ready for Inspection EVAN COOPER
Final 11/8/2022 Corrections Issued EVAN COOPER
Green Building Final 11/8/2022 Approved EVAN COOPER
Smoke Detectors 11/8/2022 Approved EVAN COOPER
ELECTRICAL-Final 11/15/2022 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Final 11/15/2022 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Final 11/15/2022 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 11/15/2022 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 12/1/2022 Approved EVAN COOPER
Final 12/1/2022 Partial Approval EVAN COOPER
HVAC-Final 12/1/2022 Approved EVAN COOPER
PLUMBING-Final 12/1/2022 Approved EVAN COOPER
Special/Order Compliance 12/2/2022 Corrections Issued EVAN COOPER
Final 9/24/2024 OK to Issue CofO ARAM AVEDISIAN