4256 S CHASE AVE 90066

Certificate Information: 4256 S CHASE AVE 90066

Application / Permit
21014-30000-01835
Plan Check / Job No.
B21WL01591
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDTION TO (E) 1-STORY SFD WITH INTERIOR REMODEL TO (E) SFD
Permit Issued
Issued on 7/29/2021
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2021 APPLICANT
Assigned to Plan Check Engineer 4/14/2021 ALFREDO JARA
Corrections Issued 4/14/2021 ALFREDO JARA
Applicant returned to address corrections 7/20/2021 MANUEL GARCIA
Plan Check Approved 7/29/2021 MANUEL GARCIA
Issued 7/29/2021 APPLICANT
CofO in Progress 3/10/2023 HERBERT GIRON
Permit Finaled 3/15/2023 DANIEL ORRANTE
CofO Issued 3/15/2023 DANIEL ORRANTE
Permit Finaled 3/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 7/4/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/12/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 7/13/2021 HISASHI KOBAYAKAWA

Contact Information

Contractor Baker Mick Construction Inc; Lic. No.: 970371-B 17535 BULLOCK STREET      ENCINO, CA 91316
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/20/2021 Corrections Issued JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 9/23/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Partial Approval DAVID FEILER
Underground Mechanical 10/20/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Approved JOHN KAYON
BUILDING-Rough-Frame 2/10/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 2/10/2022 Approved DAVID FEILER
Green Building Rough 2/10/2022 Approved DAVID FEILER
HVAC-Rough 2/10/2022 Partial Approval DAVID FEILER
Interior/Exterior Lathing 2/10/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 2/10/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 2/22/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 2/22/2022 Approved JESUS RODRIGUEZ
Insulation 2/22/2022 Conditional Approval JESUS RODRIGUEZ
Drywall Nailing 3/8/2022 Approved JESUS RODRIGUEZ
Insulation 3/8/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/21/2022 Approved STEPHANIE SWANSON
Shower Pan 3/21/2022 Approved STEPHANIE SWANSON
Pre-Inspection 10/12/2022 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 11/15/2022 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 11/15/2022 Approved HERBERT GIRON
PLUMBING-Final 11/15/2022 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Approved HERBERT GIRON
Smoke Detectors 11/15/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 11/17/2022 Approved HERBERT GIRON
Final 11/17/2022 Corrections Issued HERBERT GIRON
Green Building Final 11/17/2022 Approved HERBERT GIRON
HVAC-Final 11/17/2022 Corrections Issued HERBERT GIRON
Pre-Inspection 11/17/2022 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 11/17/2022 Approved HERBERT GIRON
Final 1/26/2023 Corrections Issued HERBERT GIRON
HVAC-Final 1/26/2023 Approved HERBERT GIRON
Final 3/10/2023 OK to Issue CofO HERBERT GIRON