623 N LUCERNE BLVD 90004

Certificate Information: 623 N LUCERNE BLVD 90004

Application / Permit
21014-30000-01830
Plan Check / Job No.
B21WL01584
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel, Ground Floor and 2-Story Addition to (E) 1-Story S.F.D
Permit Issued
Issued on 8/2/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 DAVID CASTILLO
Corrections Issued 5/24/2021 DAVID CASTILLO
Quality Review Completed 6/7/2021 TARIK SAOUD
Applicant returned to address corrections 10/26/2021 DAVID CASTILLO
Applicant returned to address corrections 2/1/2022 DAVID CASTILLO
Building Plans Picked Up 2/2/2022 APPLICANT
Applicant returned to address corrections 4/7/2022 DAVID CASTILLO
Plan Check Approved 7/29/2022 DAVID CASTILLO
Issued 8/2/2022 APPLICANT
CofO in Progress 5/10/2024 JEFFREY MEAD
CofO Issued 5/22/2024 DEROLD HAUFF
Permit Finaled 5/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 8/21/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 8/27/2021 THOMAS LANG
Sewer availability Cleared 8/27/2021 THOMAS LANG
Trees in Parkway Cleared 2/16/2022 ADALBERTO VERA
Low Impact Development Cleared 3/29/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 5/11/2022 THAN WIN

Contact Information

Contractor Owner-Builder       ,
Engineer Haro,, Ruben; Lic. No.: C72213 355 N LANTANA ST STE 492      CAMARILLO, CA 93010
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/1/2022 Partial Approval JEFFREY MEAD
Deputy Wood Construction 9/1/2022 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 9/6/2022 Partial Approval JEFFREY MEAD
METHANE-Barrier 9/6/2022 Approved JEFFREY MEAD
METHANE-Subgrade 9/6/2022 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval JEFFREY MEAD
Deputy Wood Construction 11/2/2022 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Partial Approval JEFFREY MEAD
HVAC-Rough 1/12/2023 Approved JEFFREY MEAD
Deputy Wood Construction 1/13/2023 Partial Approval JEFFREY MEAD
Deputy Wood Construction 1/25/2023 Approved JEFFREY MEAD
ELECTRICAL-Rough 1/25/2023 Corrections Issued JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Approved JEFFREY MEAD
HVAC-Rough 1/25/2023 Partial Approval JEFFREY MEAD
PLUMBING-Rough 1/25/2023 Partial Approval JEFFREY MEAD
Deputy Wood Construction 1/26/2023 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 2/3/2023 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 2/3/2023 Not Ready for Inspection JEFFREY MEAD
Green Building Rough 2/3/2023 Not Ready for Inspection JEFFREY MEAD
Interior/Exterior Lathing 2/3/2023 Not Ready for Inspection JEFFREY MEAD
METHANE-Rough 2/3/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 2/3/2023 Not Ready for Inspection JEFFREY MEAD
Wood Frame 2/3/2023 Not Ready for Inspection JEFFREY MEAD
Insulation 2/28/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 2/28/2023 Approved JEFFREY MEAD
Drywall Nailing 3/17/2023 Partial Approval JEFFREY MEAD
Green Building Rough 3/17/2023 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 3/21/2023 Approved JEFFREY MEAD
HVAC-Rough 3/21/2023 Approved JEFFREY MEAD
PLUMBING-Rough 3/21/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 3/23/2023 Partial Approval JEFFREY MEAD
Shower Pan 3/23/2023 Partial Approval JEFFREY MEAD
Sewer 7/10/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 2/8/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Drywall Nailing 2/8/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 2/8/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/8/2024 Approved ALIZAH MAYAGOITIA
Green Building Final 2/8/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 2/8/2024 Approved ALIZAH MAYAGOITIA
METHANE-Final 2/8/2024 Approved ALIZAH MAYAGOITIA
METHANE-Rough 2/8/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/8/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 2/8/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/26/2024 Partial Approval JEFFREY MEAD
Drywall Nailing 2/26/2024 Approved JEFFREY MEAD
Final 2/26/2024 Not Ready for Inspection JEFFREY MEAD
Green Building Final 2/26/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 2/26/2024 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 3/22/2024 Partial Approval JEFFREY MEAD
Final 3/22/2024 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Approved JEFFREY MEAD
Smoke Detectors 3/22/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 4/26/2024 Not Ready for Inspection JEFFREY MEAD
Final 4/26/2024 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 5/9/2024 Approved JEFFREY MEAD
Final 5/9/2024 OK to Issue CofO JEFFREY MEAD