623 N LUCERNE BLVD 90004
Certificate Information: 623 N LUCERNE BLVD 90004
- Application / Permit
- 21014-30000-01830
- Plan Check / Job No.
- B21WL01584
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel, Ground Floor and 2-Story Addition to (E) 1-Story S.F.D
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | DAVID CASTILLO |
| Corrections Issued | 5/24/2021 | DAVID CASTILLO |
| Quality Review Completed | 6/7/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 10/26/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 2/1/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 2/2/2022 | APPLICANT |
| Applicant returned to address corrections | 4/7/2022 | DAVID CASTILLO |
| Plan Check Approved | 7/29/2022 | DAVID CASTILLO |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 5/10/2024 | JEFFREY MEAD |
| CofO Issued | 5/22/2024 | DEROLD HAUFF |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 8/21/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2021 | THOMAS LANG |
| Sewer availability | Cleared | 8/27/2021 | THOMAS LANG |
| Trees in Parkway | Cleared | 2/16/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 3/29/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 5/11/2022 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Haro,, Ruben; Lic. No.: C72213 | 355 N LANTANA ST STE 492 CAMARILLO, CA 93010 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/1/2022 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 9/1/2022 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/6/2022 | Partial Approval | JEFFREY MEAD |
| METHANE-Barrier | 9/6/2022 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 9/6/2022 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 11/2/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2023 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 1/12/2023 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 1/13/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 1/25/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/25/2023 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 1/25/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 1/25/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 1/26/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 2/3/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 2/3/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 2/3/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Interior/Exterior Lathing | 2/3/2023 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 2/3/2023 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 2/3/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Wood Frame | 2/3/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Insulation | 2/28/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 2/28/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 3/17/2023 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 3/17/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 3/21/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 3/21/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 3/21/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/23/2023 | Partial Approval | JEFFREY MEAD |
| Shower Pan | 3/23/2023 | Partial Approval | JEFFREY MEAD |
| Sewer | 7/10/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 2/8/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/8/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 2/8/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/8/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 2/8/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 2/8/2024 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Final | 2/8/2024 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Rough | 2/8/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/8/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/8/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/26/2024 | Partial Approval | JEFFREY MEAD |
| Drywall Nailing | 2/26/2024 | Approved | JEFFREY MEAD |
| Final | 2/26/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 2/26/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 2/26/2024 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/22/2024 | Partial Approval | JEFFREY MEAD |
| Final | 3/22/2024 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 3/22/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/26/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 4/26/2024 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/9/2024 | Approved | JEFFREY MEAD |
| Final | 5/9/2024 | OK to Issue CofO | JEFFREY MEAD |