23056 W ERWIN ST 91367

Certificate Information: 23056 W ERWIN ST 91367

Application / Permit
21014-30000-01725
Plan Check / Job No.
B21WL01531
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITTION TO AND AND CONVERSION OF EXISTING ALQ INTO AN ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 8/23/2021
Issuing Office
Current Status
CofO Issued on 2/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/9/2021 RICHARD GARCIA
Corrections Issued 4/11/2021 RICHARD GARCIA
Applicant returned to address corrections 7/31/2021 JASON JANGADA
Plan Check Approved 8/11/2021 MANUEL GARCIA
Issued 8/23/2021 APPLICANT
CofO in Progress 1/19/2022 TROY SANDERS
Permit Finaled 2/23/2022 JOHN JANSON
CofO Issued 2/23/2022 JOHN JANSON
Permit Finaled 2/23/2022 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/27/2021 GUILLERMO PETRA
ZI Cleared 5/13/2021 LOUIS ORTEGA
Address approval Cleared 5/18/2021 ABDULLAH SADOZAI
Hydrant and Access approval Cleared 7/1/2021 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 7/28/2021 ABDULLAH SADOZAI
Sewer availability Cleared 7/28/2021 ABDULLAH SADOZAI
Grading Pre-Inspection Cleared 7/30/2021 RICHARD GARCIA
ZA Case Cleared 8/3/2021 LOUIS ORTEGA

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 11/23/2021 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 11/23/2021 Approved TROY SANDERS
Drywall Nailing 12/2/2021 Approved TROY SANDERS
Insulation 12/2/2021 Approved TROY SANDERS
Interior/Exterior Lathing 12/2/2021 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 1/18/2022 Approved TROY SANDERS
Final 1/18/2022 OK to Issue CofO TROY SANDERS
Green Building Final 1/18/2022 Approved TROY SANDERS
Green Building Rough 1/18/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 1/18/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 1/18/2022 Approved TROY SANDERS