3541 S ASHWOOD AVE 90066

Certificate Information: 3541 S ASHWOOD AVE 90066

Application / Permit
21014-30000-01695
Plan Check / Job No.
B21WL01510
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
remodel and 2nd level addition at main house
Permit Issued
Issued on 10/5/2021
Issuing Office
Current Status
CofO Issued on 11/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 FELIPE HERNANDEZ
Corrections Issued 4/16/2021 FELIPE HERNANDEZ
Quality Review Completed 4/26/2021 TARIK SAOUD
Applicant returned to address corrections 8/30/2021 FELIPE HERNANDEZ
Plan Check Approved 9/28/2021 FELIPE HERNANDEZ
Issued 10/5/2021 APPLICANT
CofO in Progress 11/15/2022 RICHARD STEINBACH
Permit Finaled 11/17/2022 DANIEL ORRANTE
CofO Issued 11/17/2022 DANIEL ORRANTE
Permit Finaled 11/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/23/2021 DINAH GARIN
Sewer availability Cleared 6/23/2021 DINAH GARIN
Hydrant and Access approval Cleared 8/20/2021 ROBERT DUFF
Low Impact Development Cleared 9/1/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/1/2021 DINAH GARIN
Specific Plan Cleared 9/9/2021 PETE EYRE
Grading Pre-Inspection Cleared 9/28/2021 FELIPE HERNANDEZ

Contact Information

Architect Carson,, Thomas Darall; Lic. No.: C24160 1239 1/2 APPLETON WAY      VENICE, CA 90291
Contractor Basix Designs & Remodeling Inc; Lic. No.: 769443-B 650 S HIGHLAND AVE      LOS ANGELES, CA 90036
Engineer Germiyanoglu,, Ismail; Lic. No.: S1505 144 N STANLEY DR      BEVERLY HILLS, CA 90211

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/1/2021 Approved ENRIQUE MIRELES
Underground Mechanical 2/7/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 3/18/2022 Corrections Issued PATRICK QUALEY
Interior/Exterior Lathing 3/18/2022 Partial Approval PATRICK QUALEY
PLUMBING-Rough 3/18/2022 Approved PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Approved ANDREW NAVE
HVAC-Rough 4/1/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 4/1/2022 Partial Approval ANDREW NAVE
Shower Pan 4/1/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 4/28/2022 Corrections Issued PATRICK QUALEY
Green Building Rough 4/28/2022 Approved PATRICK QUALEY
Insulation 4/28/2022 Approved PATRICK QUALEY
Interior/Exterior Lathing 4/28/2022 Conditional Approval PATRICK QUALEY
Drywall Nailing 5/16/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 9/21/2022 Corrections Issued JESUS RODRIGUEZ
Final 9/21/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 9/21/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 9/21/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 9/21/2022 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 9/21/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/8/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 11/8/2022 Approved JESUS RODRIGUEZ
Final 11/8/2022 Conditional Approval JESUS RODRIGUEZ
Green Building Final 11/8/2022 Approved JESUS RODRIGUEZ
HVAC-Final 11/8/2022 Approved JESUS RODRIGUEZ
Service/Power Release 11/8/2022 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 11/8/2022 Approved JESUS RODRIGUEZ