409 W 110TH ST 90061
Certificate Information: 409 W 110TH ST 90061
- Application / Permit
- 21014-30000-01686
- Plan Check / Job No.
- B21WL01486
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING SFD. ALL CONSTRUCTION PER WFPP
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2021 | RICHARD GARCIA |
| Corrections Issued | 4/11/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 9/9/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 2/23/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/11/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/29/2022 | EDWIN ESPIN |
| Plan Check Approved | 5/23/2022 | RICHARD GARCIA |
| Issued | 6/1/2022 | APPLICANT |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| CofO in Progress | 2/8/2023 | JAMES CHAVEZ |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
| CofO Issued | 3/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/6/2021 | RENZ SORIANO |
| ZI | Cleared | 8/6/2021 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/31/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/24/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/30/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 9/19/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 9/22/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 10/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Approved | JOHN KLARIN |
| Insulation | 10/24/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/24/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 10/28/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 11/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 11/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 11/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 11/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Final | 11/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Rough | 11/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Not Ready | JOHN KLARIN |
| Smoke Detectors | 11/22/2022 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/27/2023 | Approved | JAMES CHAVEZ |
| Final | 1/27/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 1/27/2023 | Approved | JAMES CHAVEZ |
| Green Building Final | 1/27/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Rough | 1/27/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Final | 1/27/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 1/27/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Approved | JAMES CHAVEZ |
| Smoke Detectors | 1/27/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 2/8/2023 | Approved | JAMES CHAVEZ |
| Final | 2/8/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 2/8/2023 | Approved | JAMES CHAVEZ |
| HVAC-Final | 2/8/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 2/8/2023 | Approved | JAMES CHAVEZ |