325 N KENTER AVE 90049

Certificate Information: 325 N KENTER AVE 90049

Application / Permit
21014-30000-01669
Plan Check / Job No.
B21WL01458
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND INTERIOR ALTERATION TO AN EXISTING SFD. PER ENGINEERING DESIGN
Permit Issued
Issued on 11/22/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 ALFREDO JARA
Corrections Issued 4/28/2021 ALFREDO JARA
Applicant returned to address corrections 7/7/2022 JASON JANGADA
Applicant returned to address corrections 7/19/2022 DAVID CASTILLO
Plan Check Approved 8/4/2022 JASON JANGADA
Building Plans Picked Up 8/5/2022 APPLICANT
Issued 11/22/2022 APPLICANT
CofO in Progress 7/19/2025 MICHAEL PELHAM
Permit Finaled 7/19/2025 RICHARD STEINBACH
Permit Finaled 7/19/2025 RICHARD STEINBACH
CofO Issued 7/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development Cleared 5/6/2022 JULIAN SUNG
Grading Pre-Inspection Cleared 7/7/2022 ALFREDO JARA
Roof/Waste drainage to street Cleared 7/7/2022 DINAH GARIN
Sewer availability Cleared 7/7/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/8/2022 DINAH GARIN

Contact Information

Architect Williams,, Samuel M; Lic. No.: C26806 17260 PRAIRIE STREET      NORTHRIDGE, CA 91325
Contractor Wards American Building Concepts Inc; Lic. No.: 754779-B 481 CALLE ARROYO      THOUSAND OAKS, CA 91360
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/27/2022 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 12/27/2022 Partial Inspection STEPHANIE SWANSON
Deputy Drilled-In Anchors 12/28/2022 No Access for Inspection DAVID FEILER
Footing/Foundation/Slab 1/4/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 2/3/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 2/3/2023 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2023 No Access for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/3/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 4/18/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 4/18/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 4/18/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 4/21/2023 Approved KEVIN SARGSYAN
HVAC-Rough 4/21/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 4/21/2023 Approved KEVIN SARGSYAN
Wood Frame 5/2/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/4/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 5/19/2023 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 5/23/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Approved JESUS RODRIGUEZ
Green Building Rough 5/23/2023 Approved JESUS RODRIGUEZ
HVAC-Final 5/23/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 5/23/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/23/2023 Approved JESUS RODRIGUEZ
Shower Pan 5/23/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/2/2023 Approved KEVIN SARGSYAN
Insulation 6/6/2023 Approved KEVIN SARGSYAN
Drywall Nailing 6/12/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Final 10/30/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 10/30/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 10/30/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 10/30/2023 Approved ARAM AVEDISIAN
Final 11/1/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 11/1/2023 Approved ARAM AVEDISIAN
HVAC-Final 11/1/2023 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 11/1/2023 Approved ARAM AVEDISIAN
HVAC-Final 11/8/2023 Approved CARLOS MATAMOROS
Final 7/19/2025 OK to Issue CofO MICHAEL PELHAM