3491 S FEDERAL AVE 90066

Certificate Information: 3491 S FEDERAL AVE 90066

Application / Permit
21014-30000-01607
Plan Check / Job No.
B21WL01386
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
major remodel and addition to create 2-story SFD with attached garage.
Permit Issued
Issued on 11/23/2021
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 TARIK SAOUD
Corrections Issued 5/5/2021 TARIK SAOUD
Quality Review Completed 5/12/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 11/12/2021 TARIK SAOUD
Building Plans Picked Up 11/15/2021 APPLICANT
Issued 11/23/2021 APPLICANT
CofO in Progress 10/25/2022 JOHNNY MIRANDA
Permit Finaled 10/28/2022 DANIEL ORRANTE
CofO Issued 10/28/2022 DANIEL ORRANTE
Permit Finaled 10/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 5/21/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/27/2021 DINAH GARIN
Sewer availability Cleared 5/27/2021 DINAH GARIN
Hydrant and Access approval Cleared 7/16/2021 MATTHEW CRAIG
Specific Plan Cleared 7/30/2021 PETE EYRE
Low Impact Development Cleared 9/12/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/15/2021 DINAH GARIN
Trees in Parkway Cleared 10/13/2021 ADALBERTO VERA
Frnt yard landscape/Water mgmt Cleared 10/14/2021 ANACANY HURTADO
Grading Pre-Inspection Cleared 11/12/2021 TARIK SAOUD

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Zepeda General Building; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/25/2022 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 2/3/2022 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 2/3/2022 Approved JOHNNY MIRANDA
Special/Order Compliance 2/8/2022 Corrections Issued JOHNNY MIRANDA
Pre-Inspection 2/18/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Conditional Approval JOHNNY MIRANDA
ELECTRICAL-Rough 4/1/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 4/1/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 4/1/2022 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 4/5/2022 Approved JOHNNY MIRANDA
Gas Test 4/5/2022 Partial Approval JOHNNY MIRANDA
HVAC-Rough 4/5/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 4/5/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 4/29/2022 Corrections Issued JOHNNY MIRANDA
Green Building Rough 4/29/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 4/29/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 5/3/2022 Approved JOHNNY MIRANDA
Green Building Rough 5/3/2022 Approved JOHNNY MIRANDA
Deputy Wood Construction 5/4/2022 Conditional Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 5/5/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Approved JOHNNY MIRANDA
Insulation 5/5/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/5/2022 Partial Approval JOHNNY MIRANDA
Drywall Nailing 5/9/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/8/2022 Approved KENNETH NAGLE
Shower Pan 6/8/2022 Not Ready for Inspection KENNETH NAGLE
Interior/Exterior Lathing 6/14/2022 Approved JOHNNY MIRANDA
Shower Pan 6/14/2022 Approved JOHNNY MIRANDA
Gas Test 8/1/2022 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 9/27/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Final 9/27/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 9/27/2022 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Final 10/3/2022 Approved JOHNNY MIRANDA
Final 10/3/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 10/3/2022 Approved JOHNNY MIRANDA
HVAC-Final 10/3/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 10/3/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 10/3/2022 Approved JOHNNY MIRANDA
Final 10/21/2022 Conditional Approval JOHNNY MIRANDA