12250 W DARLINGTON AVE 90049
Certificate Information: 12250 W DARLINGTON AVE 90049
- Application / Permit
- 21014-30000-01529
- Plan Check / Job No.
- B21WL01343
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major Remodel with 2-Story Addition to (E) S.F.D
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- CofO Issued on 6/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | DAVID CASTILLO |
| Corrections Issued | 4/6/2021 | DAVID CASTILLO |
| Quality Review Completed | 4/16/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 9/28/2021 | DAVID CASTILLO |
| Plan Check Approved | 10/8/2021 | DAVID CASTILLO |
| Issued | 10/15/2021 | APPLICANT |
| CofO in Progress | 6/21/2023 | JESUS PINEDA |
| CofO in Progress | 6/21/2023 | JESUS PINEDA |
| Permit Finaled | 6/23/2023 | KENNETH NAGLE |
| CofO Issued | 6/23/2023 | KENNETH NAGLE |
| Permit Finaled | 6/23/2023 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 5/11/2021 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 9/3/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/4/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Zepeda General Building; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/18/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 12/6/2021 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/6/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/21/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/28/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/14/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/19/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 7/19/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/19/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 7/22/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 7/28/2022 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 8/23/2022 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/23/2022 | Approved | STEPHANIE SWANSON |
| Shower Pan | 9/14/2022 | Corrections Issued | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/16/2022 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/5/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 5/17/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 5/17/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 5/17/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 5/22/2023 | Not Ready for Inspection | JESUS PINEDA |
| Gas Test | 5/22/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 5/22/2023 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 5/22/2023 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 5/25/2023 | Conditional Approval | JESUS PINEDA |
| Gas Test | 5/25/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 5/25/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 5/25/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 6/2/2023 | Approved | JESUS PINEDA |
| Final | 6/2/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 6/2/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 6/2/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 6/2/2023 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 6/2/2023 | Approved | JESUS PINEDA |
| Final | 6/20/2023 | OK to Issue CofO | JESUS PINEDA |