12250 W DARLINGTON AVE 90049

Certificate Information: 12250 W DARLINGTON AVE 90049

Application / Permit
21014-30000-01529
Plan Check / Job No.
B21WL01343
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major Remodel with 2-Story Addition to (E) S.F.D
Permit Issued
Issued on 10/15/2021
Issuing Office
Current Status
CofO Issued on 6/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 DAVID CASTILLO
Corrections Issued 4/6/2021 DAVID CASTILLO
Quality Review Completed 4/16/2021 TARIK SAOUD
Applicant returned to address corrections 9/28/2021 DAVID CASTILLO
Plan Check Approved 10/8/2021 DAVID CASTILLO
Issued 10/15/2021 APPLICANT
CofO in Progress 6/21/2023 JESUS PINEDA
CofO in Progress 6/21/2023 JESUS PINEDA
Permit Finaled 6/23/2023 KENNETH NAGLE
CofO Issued 6/23/2023 KENNETH NAGLE
Permit Finaled 6/23/2023 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/11/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/11/2021 HISASHI KOBAYAKAWA
Low Impact Development Cleared 9/3/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/4/2021 HISASHI KOBAYAKAWA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Zepeda General Building; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280
Engineer Namdar,, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2021 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 12/6/2021 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/6/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 6/21/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/21/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/28/2022 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/14/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/19/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 7/19/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/19/2022 Partial Approval OGANES TARAKHCHYAN
Insulation 7/22/2022 Corrections Issued STEPHANIE SWANSON
Insulation 7/28/2022 Approved STEPHANIE SWANSON
Drywall Nailing 8/23/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 8/23/2022 Approved STEPHANIE SWANSON
Shower Pan 9/14/2022 Corrections Issued JOHN KIDWELL
Interior/Exterior Lathing 9/16/2022 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 10/5/2022 Approved EVAN COOPER
ELECTRICAL-Final 5/17/2023 Corrections Issued HERBERT GIRON
HVAC-Final 5/17/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 5/17/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 5/22/2023 Not Ready for Inspection JESUS PINEDA
Gas Test 5/22/2023 Corrections Issued JESUS PINEDA
HVAC-Final 5/22/2023 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 5/22/2023 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 5/25/2023 Conditional Approval JESUS PINEDA
Gas Test 5/25/2023 Approved JESUS PINEDA
HVAC-Final 5/25/2023 Corrections Issued JESUS PINEDA
PLUMBING-Final 5/25/2023 Approved JESUS PINEDA
ELECTRICAL-Final 6/2/2023 Approved JESUS PINEDA
Final 6/2/2023 Corrections Issued JESUS PINEDA
Green Building Final 6/2/2023 Approved JESUS PINEDA
HVAC-Final 6/2/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Approved JESUS PINEDA
Smoke Detectors 6/2/2023 Approved JESUS PINEDA
Final 6/20/2023 OK to Issue CofO JESUS PINEDA