1310 E PRESTON WAY 90291

Certificate Information: 1310 E PRESTON WAY 90291

Application / Permit
21014-30000-01518
Plan Check / Job No.
B21WL01329
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition and major remodel
Permit Issued
Issued on 7/19/2021
Issuing Office
Current Status
CofO Issued on 9/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 FELIPE HERNANDEZ
Corrections Issued 4/6/2021 FELIPE HERNANDEZ
Quality Review Completed 4/16/2021 TARIK SAOUD
Applicant returned to address corrections 4/19/2021 FELIPE HERNANDEZ
Plan Check Approved 6/23/2021 FELIPE HERNANDEZ
Issued 7/19/2021 APPLICANT
CofO in Progress 9/7/2022 DAVID FEILER
Permit Finaled 9/9/2022 DANIEL ORRANTE
CofO Issued 9/9/2022 DANIEL ORRANTE
Permit Finaled 9/9/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 4/13/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/22/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/22/2021 HISASHI KOBAYAKAWA
Low Impact Development Cleared 6/10/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 6/21/2021 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 6/23/2021 FELIPE HERNANDEZ

Contact Information

Contractor Southland Building & Remodel Company; Lic. No.: 894311-B 1324 WEST ROSECRANS AVENUE      COMPTON, CA 90222

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/17/2021 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 8/26/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 8/26/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Partial Approval JOHNNY MIRANDA
Deputy Wood Construction 11/18/2021 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 1/7/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 1/7/2022 Approved DAVID FEILER
Green Building Rough 1/7/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 1/7/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 1/7/2022 Approved DAVID FEILER
ELECTRICAL-Rough 1/27/2022 No Access for Inspection EVAN COOPER
HVAC-Rough 1/27/2022 No Access for Inspection EVAN COOPER
Wood Frame 1/27/2022 No Access for Inspection EVAN COOPER
ELECTRICAL-Rough 1/28/2022 Approved DAVID FEILER
HVAC-Rough 1/28/2022 Approved DAVID FEILER
Wood Frame 1/28/2022 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 3/2/2022 Approved DAVID FEILER
Green Building Rough 3/2/2022 Approved DAVID FEILER
Interior/Exterior Lathing 3/2/2022 Partial Approval DAVID FEILER
Verify Sprinkler Sign Off 3/2/2022 Approved DAVID FEILER
Insulation 3/7/2022 Approved DAVID FEILER
Drywall Nailing 3/14/2022 Approved CLAYTON GRAHAM
Shower Pan 3/14/2022 Partial Approval CLAYTON GRAHAM
Interior/Exterior Lathing 3/21/2022 Approved DAVID FEILER
Shower Pan 3/21/2022 Approved DAVID FEILER
Gas Test 8/22/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 8/25/2022 Corrections Issued DAVID FEILER
Final 8/25/2022 Not Ready for Inspection DAVID FEILER
Gas Test 8/25/2022 Corrections Issued DAVID FEILER
Green Building Final 8/25/2022 Not Ready for Inspection DAVID FEILER
HVAC-Final 8/25/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 8/25/2022 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 8/25/2022 SGSOV Approved DAVID FEILER
Service/Power Release 8/25/2022 Not Ready for Inspection DAVID FEILER
Smoke Detectors 8/25/2022 Approved DAVID FEILER
ELECTRICAL-Final 8/29/2022 Partial Approval DAVID FEILER
Final 8/29/2022 Corrections Issued DAVID FEILER
Gas Test 8/29/2022 Approved DAVID FEILER
Green Building Final 8/29/2022 Corrections Issued DAVID FEILER
HVAC-Final 8/29/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 8/29/2022 Approved DAVID FEILER
Service/Power Release 8/29/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 8/31/2022 Approved DAVID FEILER
Final 8/31/2022 Partial Approval DAVID FEILER
Green Building Final 8/31/2022 Approved DAVID FEILER
HVAC-Final 8/31/2022 Approved DAVID FEILER
PLUMBING-Final 8/31/2022 Approved DAVID FEILER
Service/Power Release 8/31/2022 Approved DAVID FEILER
Final 9/7/2022 OK to Issue CofO DAVID FEILER