1310 E PRESTON WAY 90291
Certificate Information: 1310 E PRESTON WAY 90291
- Application / Permit
- 21014-30000-01518
- Plan Check / Job No.
- B21WL01329
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition and major remodel
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 4/6/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 4/16/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 4/19/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 6/23/2021 | FELIPE HERNANDEZ |
| Issued | 7/19/2021 | APPLICANT |
| CofO in Progress | 9/7/2022 | DAVID FEILER |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 4/13/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/22/2021 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 6/10/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/21/2021 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 6/23/2021 | FELIPE HERNANDEZ |
Contact Information
| Contractor | Southland Building & Remodel Company; Lic. No.: 894311-B | 1324 WEST ROSECRANS AVENUE COMPTON, CA 90222 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/17/2021 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 8/26/2021 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 8/26/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 11/18/2021 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 1/7/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 1/7/2022 | Approved | DAVID FEILER |
| Green Building Rough | 1/7/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 1/7/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 1/7/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 1/27/2022 | No Access for Inspection | EVAN COOPER |
| HVAC-Rough | 1/27/2022 | No Access for Inspection | EVAN COOPER |
| Wood Frame | 1/27/2022 | No Access for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 1/28/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 1/28/2022 | Approved | DAVID FEILER |
| Wood Frame | 1/28/2022 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 3/2/2022 | Approved | DAVID FEILER |
| Green Building Rough | 3/2/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/2/2022 | Partial Approval | DAVID FEILER |
| Verify Sprinkler Sign Off | 3/2/2022 | Approved | DAVID FEILER |
| Insulation | 3/7/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 3/14/2022 | Approved | CLAYTON GRAHAM |
| Shower Pan | 3/14/2022 | Partial Approval | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 3/21/2022 | Approved | DAVID FEILER |
| Shower Pan | 3/21/2022 | Approved | DAVID FEILER |
| Gas Test | 8/22/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 8/25/2022 | Corrections Issued | DAVID FEILER |
| Final | 8/25/2022 | Not Ready for Inspection | DAVID FEILER |
| Gas Test | 8/25/2022 | Corrections Issued | DAVID FEILER |
| Green Building Final | 8/25/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Final | 8/25/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Final | 8/25/2022 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Approved | DAVID FEILER |
| Service/Power Release | 8/25/2022 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 8/25/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 8/29/2022 | Partial Approval | DAVID FEILER |
| Final | 8/29/2022 | Corrections Issued | DAVID FEILER |
| Gas Test | 8/29/2022 | Approved | DAVID FEILER |
| Green Building Final | 8/29/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 8/29/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 8/29/2022 | Approved | DAVID FEILER |
| Service/Power Release | 8/29/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 8/31/2022 | Approved | DAVID FEILER |
| Final | 8/31/2022 | Partial Approval | DAVID FEILER |
| Green Building Final | 8/31/2022 | Approved | DAVID FEILER |
| HVAC-Final | 8/31/2022 | Approved | DAVID FEILER |
| PLUMBING-Final | 8/31/2022 | Approved | DAVID FEILER |
| Service/Power Release | 8/31/2022 | Approved | DAVID FEILER |
| Final | 9/7/2022 | OK to Issue CofO | DAVID FEILER |